13440 W TIARA ST 91401

Certificate Information: 13440 W TIARA ST 91401

Application / Permit
22014-20000-00354
Plan Check / Job No.
B22VN01259
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW PATIO COVER ADDITION TO & REMODEL OF EXISTING SINGLE FAMILY DWELLING.
Permit Issued
Issued on 4/28/2022
Issuing Office
Valley
Current Status
CofO Issued on 12/17/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/28/2022 APPLICANT
Assigned to Plan Check Engineer 2/17/2022 MAHNAZ NOURHASHEMI
Corrections Issued 3/17/2022 MANUEL MONTUFAR
Quality Review Completed 3/21/2022 EUGENE BARBEAU
Building Plans Picked Up 3/23/2022 APPLICANT
Plan Check Approved 4/20/2022 MANUEL MONTUFAR
Issued 4/28/2022 APPLICANT
CofO in Progress 12/16/2022 ROBERT GOLD
CofO Issued 12/17/2022 MICHAEL SMITH
Permit Finaled 12/17/2022 MICHAEL SMITH

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 3/23/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 3/24/2022 CARLOS AGUILERA
Sewer availability Cleared 3/24/2022 CARLOS AGUILERA

Contact Information

Architect Stockton,, Richard Kenneth; Lic. No.: C35492 20140 ZIMMERMAN PLACE      SANTA CLARITA, CA 91390
Contractor Owner-Builder       ,
Engineer Warling,, Jeffrey Paul; Lic. No.: C43743 1792 PEREGRINE CT      SIMI VALLEY, CA 93065

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/1/2022 Approved CHRISTOPHE COCHRAN
Footing/Foundation/Slab 6/1/2022 Partial Approval CHRISTOPHE COCHRAN
METHANE-Barrier 6/1/2022 Not Ready for Inspection CHRISTOPHE COCHRAN
METHANE-Subgrade 6/1/2022 Not Ready for Inspection CHRISTOPHE COCHRAN
Footing/Foundation/Slab 6/10/2022 Partial Approval CHRISTOPHE COCHRAN
METHANE-Barrier 6/10/2022 Not Ready for Inspection CHRISTOPHE COCHRAN
METHANE-Subgrade 6/10/2022 Not Ready for Inspection CHRISTOPHE COCHRAN
Footing/Foundation/Slab 6/17/2022 Approved CHRISTOPHE COCHRAN
METHANE-Barrier 6/17/2022 Approved CHRISTOPHE COCHRAN
METHANE-Rough 6/17/2022 Approved CHRISTOPHE COCHRAN
METHANE-Subgrade 6/17/2022 Approved CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 7/7/2022 Approved RAFAEL CORTES
ELECTRICAL-Rough 7/18/2022 Not Ready for Inspection RAFAEL CORTES
Floor/Roof Diaphrgm/Shear Wall 7/18/2022 Conditional Approval RAFAEL CORTES
PLUMBING-Rough 7/18/2022 Partial Approval RAFAEL CORTES
Drywall Nailing 7/21/2022 Not Ready for Inspection RAFAEL CORTES
ELECTRICAL-Rough 7/21/2022 Approved RAFAEL CORTES
Floor/Roof Diaphrgm/Shear Wall 7/21/2022 Approved RAFAEL CORTES
HVAC-Rough 7/21/2022 Approved RAFAEL CORTES
PLUMBING-Rough 7/21/2022 Corrections Issued RAFAEL CORTES
Shower Pan 7/21/2022 Partial Approval RAFAEL CORTES
Insulation 7/26/2022 Approved RAFAEL CORTES
Interior/Exterior Lathing 7/26/2022 Partial Approval RAFAEL CORTES
PLUMBING-Rough 7/26/2022 Partial Approval RAFAEL CORTES
Shower Pan 7/26/2022 Approved RAFAEL CORTES
Drywall Nailing 8/9/2022 Approved RAFAEL CORTES
BUILDING-Rough-Frame 10/18/2022 Approved CHRISTOPHER DELLEFIELD
ELECTRICAL-Final 10/18/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Final 10/18/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Green Building Final 10/18/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Green Building Rough 10/18/2022 Approved CHRISTOPHER DELLEFIELD
HVAC-Final 10/18/2022 Corrections Issued CHRISTOPHER DELLEFIELD
PLUMBING-Final 10/18/2022 Corrections Issued CHRISTOPHER DELLEFIELD
SGSOV-Seismic Gas S/O Valve 10/18/2022 SGSOV Approved CHRISTOPHER DELLEFIELD
Smoke Detectors 10/18/2022 Approved CHRISTOPHER DELLEFIELD
Final 10/25/2022 Corrections Issued WILLIAM WREN
Final 11/2/2022 Corrections Issued CHRISTOPHE COCHRAN
Final 11/8/2022 Corrections Issued JOHN HAYES
Green Building Final 11/8/2022 Not Ready for Inspection JOHN HAYES
Final 11/17/2022 OK to Issue CofO CALEB MEISTER
Green Building Final 11/17/2022 Approved CALEB MEISTER