1539 N SAN YSIDRO DR 90210
Certificate Information: 1539 N SAN YSIDRO DR 90210
- Application / Permit
- 22014-20000-00350
- Plan Check / Job No.
- B22VN01213
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR REMODEL TO THE (E) SINGLE FAMILY DWELLING TO REMOVE THE (E) ATTACHED PATIO AND ADD 10'-0" x 20'-0" DINING ROOM. REMODEL THE (E) KITCHEN, BATHROOM,BEDROOM AND MASTER BATHROOM AND ADD A CLOSET.
- Permit Issued
- Issued on 7/21/2022
- Issuing Office
- Current Status
- CofO Issued on 6/14/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/27/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/8/2022 | SARKIS HARABEDIAN |
| Corrections Issued | 2/10/2022 | SARKIS HARABEDIAN |
| Plan Check Approved | 5/6/2022 | SARKIS HARABEDIAN |
| Building Plans Picked Up | 5/9/2022 | APPLICANT |
| Issued | 7/21/2022 | APPLICANT |
| Permit Finaled | 6/14/2024 | DANIEL ORRANTE |
| CofO Issued | 6/14/2024 | DANIEL ORRANTE |
| Permit Finaled | 6/14/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 2/23/2022 | VASIL MIHALEV |
| Hydrant and Access approval | Cleared | 4/6/2022 | KURT CORRAL |
| Roof/Waste drainage to street | Cleared | 4/28/2022 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 4/29/2022 | DINAH GARIN |
Contact Information
| Contractor | B S E General Construction; Lic. No.: 937428-B | P O BOX 44003 PANORAMA CITY, CA 91402 |
| Engineer | Niver,, Kenneth Earl; Lic. No.: S2554 | 10845 LINDBROOK DR STE 203 W LOS ANGELES, CA 90024 |
Inspector Information
| CARLOS MATAMOROS, (310) 914-3878 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/21/2022 | Corrections Issued | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 11/1/2022 | Approved | CHRISTOPHER WILSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/15/2022 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Deputy Drilled-In Anchors | 11/18/2022 | Conditional Approval | GERMAN RODRIGUEZ MENDOZA |
| Deputy Wood Construction | 1/26/2023 | Conditional Approval | MICHAEL PELHAM |
| Wood Frame | 3/3/2023 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| ELECTRICAL-Rough | 5/12/2023 | Corrections Issued | BRENDAN LOONEY |
| Floor/Roof Diaphrgm/Shear Wall | 5/12/2023 | Partial Approval | BRENDAN LOONEY |
| Green Building Rough | 5/12/2023 | Not Ready for Inspection | BRENDAN LOONEY |
| HVAC-Rough | 5/12/2023 | Corrections Issued | BRENDAN LOONEY |
| PLUMBING-Rough | 5/12/2023 | Approved | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 7/11/2023 | Conditional Approval | BRENDAN LOONEY |
| ELECTRICAL-Rough | 7/11/2023 | Conditional Approval | BRENDAN LOONEY |
| HVAC-Rough | 7/11/2023 | Not Ready for Inspection | BRENDAN LOONEY |
| Interior/Exterior Lathing | 7/11/2023 | Corrections Issued | BRENDAN LOONEY |
| Insulation | 7/21/2023 | Partial Approval | BRENDAN LOONEY |
| Drywall Nailing | 8/1/2023 | Partial Approval | BRENDAN LOONEY |
| Green Building Rough | 8/1/2023 | Approved | BRENDAN LOONEY |
| Interior/Exterior Lathing | 8/24/2023 | Approved | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 2/21/2024 | Approved | MEL KHACHATOURIAN |
| Drywall Nailing | 2/21/2024 | Approved | MEL KHACHATOURIAN |
| Final | 2/21/2024 | Corrections Issued | MEL KHACHATOURIAN |
| Green Building Final | 2/21/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| SGSOV-Seismic Gas S/O Valve | 2/21/2024 | SGSOV Approved | MEL KHACHATOURIAN |
| Smoke Detectors | 2/21/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Final | 3/21/2024 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Green Building Final | 3/21/2024 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Smoke Detectors | 3/21/2024 | Not Ready for Inspection | CHRISTOPHER WILSON |
| ELECTRICAL-Final | 4/3/2024 | Corrections Issued | STEPHANIE SWANSON |
| Final | 4/3/2024 | Corrections Issued | STEPHANIE SWANSON |
| Green Building Final | 4/3/2024 | Approved | STEPHANIE SWANSON |
| HVAC-Final | 4/3/2024 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Final | 4/3/2024 | Approved | STEPHANIE SWANSON |
| SGSOV-Seismic Gas S/O Valve | 4/3/2024 | SGSOV Approved | STEPHANIE SWANSON |
| Smoke Detectors | 4/3/2024 | Approved | STEPHANIE SWANSON |
| Final | 4/8/2024 | Corrections Issued | SEAN HAUPT |
| Final | 4/30/2024 | Not Ready for Inspection | SEAN HAUPT |
| Final | 6/12/2024 | Conditional Approval | STEPHANIE SWANSON |