7441 N GAYNOR AVE 91406
Certificate Information: 7441 N GAYNOR AVE 91406
- Application / Permit
- 22014-20000-00337
- Plan Check / Job No.
- B22VN01178
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 12'-6" X 15'-3" ADDITION TO AND CONVERT THE (E) 408 SF GARAGE W/ ATT 115 SF RUMPUS ROOM INTO A (N) 713 SF ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d). ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 4/3/2023
- Issuing Office
- Valley
- Current Status
- Issued on 4/3/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 2/8/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/17/2022 | ARTIN ZARUKIAN |
| Corrections Issued | 2/19/2022 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 2/23/2022 | APPLICANT |
| Applicant returned to address corrections | 3/14/2023 | ISIS ARGUETA |
| Applicant returned to address corrections | 3/21/2023 | DANIEL ABRAMYAN |
| Applicant returned to address corrections | 3/30/2023 | LUISANGEL VALENZUELA |
| Issued | 4/3/2023 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 3/21/2022 | JOSE DUARTE-DIAZ |
| Roof/Waste drainage to street | Cleared | 3/21/2022 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 4/25/2022 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 4/25/2022 | JOSE DUARTE-DIAZ |
| Low Impact Development | Cleared | 3/2/2023 | ERNEST TSE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21243 VENTURA BLVD SUITE 119 WOODLAND HILLS, CA 91364 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 1/12/2024 | Conditional Approval | DAVID MATSON |
| Footing/Foundation/Slab | 1/12/2024 | Conditional Approval | RAUL OLAGI |
| Special/Order Compliance | 1/12/2024 | Corrections Issued | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 12/3/2024 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Rough | 12/3/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Floor/Roof Diaphrgm/Shear Wall | 12/9/2024 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Rough | 12/9/2024 | Approved | SALVADOR MARTINEZ |
| ELECTRICAL-Rough | 12/23/2024 | Approved | SALVADOR MARTINEZ |
| HVAC-Rough | 12/23/2024 | Approved | SALVADOR MARTINEZ |
| Sewer | 12/23/2024 | Approved | SALVADOR MARTINEZ |
| Underground Mechanical | 12/23/2024 | Approved | SALVADOR MARTINEZ |
| Floor/Roof Diaphrgm/Shear Wall | 1/10/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Floor/Roof Diaphrgm/Shear Wall | 4/28/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Wood Frame | 6/10/2025 | Corrections Issued | JACK KARGODORIAN |
| ELECTRICAL-Rough | 6/12/2025 | Corrections Issued | MICHAEL CORTEZ |
| Floor/Roof Diaphrgm/Shear Wall | 6/12/2025 | Partial Approval | MICHAEL CORTEZ |
| BUILDING-Rough-Frame | 6/16/2025 | Corrections Issued | SALVADOR MARTINEZ |
| ELECTRICAL-Rough | 6/16/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Floor/Roof Diaphrgm/Shear Wall | 6/16/2025 | Approved | SALVADOR MARTINEZ |
| Interior/Exterior Lathing | 6/16/2025 | Partial Approval | SALVADOR MARTINEZ |
| ELECTRICAL-Rough | 6/23/2025 | Conditional Approval | RAUL OLAGI |
| Insulation | 6/23/2025 | Approved | RAUL OLAGI |
| Special/Order Compliance | 6/23/2025 | Corrections Issued | RAUL OLAGI |
| Drywall Nailing | 7/2/2025 | Approved | JOAQUIN GREENOUGH |
| Interior/Exterior Lathing | 7/2/2025 | Approved | JOAQUIN GREENOUGH |