10608 W LEDEEN DR 91342
Certificate Information: 10608 W LEDEEN DR 91342
- Application / Permit
- 22014-20000-00335
- Plan Check / Job No.
- B22VN01171
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 20' X 20' ADDITION OF AN OPEN PATIO COVER.
- Permit Issued
- Issued on 7/18/2022
- Issuing Office
- Current Status
- CofO Issued on 3/2/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/27/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/4/2022 | JESSE ARELLANO |
| Corrections Issued | 2/5/2022 | JESSE ARELLANO |
| Applicant returned to address corrections | 3/23/2022 | JESSE ARELLANO |
| Building Plans Picked Up | 3/29/2022 | APPLICANT |
| Applicant returned to address corrections | 7/8/2022 | JESSE ARELLANO |
| Issued | 7/18/2022 | APPLICANT |
| CofO in Progress | 11/8/2022 | MATTHEW NELSON |
| Permit Finaled | 3/2/2023 | MICHAEL SMITH |
| CofO Issued | 3/2/2023 | MICHAEL SMITH |
| Permit Finaled | 3/2/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 3/19/2022 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 3/22/2022 | JOSE DUARTE-DIAZ |
| ZI | Cleared | 6/14/2022 | PEGGY MALONE-BROWN |
Contact Information
| Contractor | Alum Works Inc; Lic. No.: 857189-B | 16350 VENTURA BLVD #D103 ENCINO, CA 91436 |
| Engineer | Saiyadian, Sarnaghi, Tomik; Lic. No.: C89129 | 1171 JUSTIN AVE APT 3 GLENDALE, CA 91201 |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 8/8/2022 | Corrections Issued | MATTHEW NELSON |
| ELECTRICAL-Final | 8/8/2022 | Corrections Issued | MATTHEW NELSON |
| Final | 8/8/2022 | Corrections Issued | MATTHEW NELSON |
| Footing/Foundation/Slab | 8/8/2022 | Corrections Issued | MATTHEW NELSON |
| Smoke Detectors | 8/8/2022 | Not Ready for Inspection | MATTHEW NELSON |
| BUILDING-Rough-Frame | 8/16/2022 | Not Ready for Inspection | MATTHEW NELSON |
| ELECTRICAL-Final | 8/16/2022 | Not Ready for Inspection | MATTHEW NELSON |
| Final | 8/16/2022 | Corrections Issued | MATTHEW NELSON |
| Footing/Foundation/Slab | 8/16/2022 | Not Ready for Inspection | MATTHEW NELSON |
| Smoke Detectors | 8/16/2022 | Not Ready for Inspection | MATTHEW NELSON |
| BUILDING-Rough-Frame | 9/8/2022 | Partial Approval | MATTHEW NELSON |
| ELECTRICAL-Final | 9/8/2022 | Partial Approval | MATTHEW NELSON |
| Final | 9/8/2022 | Corrections Issued | MATTHEW NELSON |
| Footing/Foundation/Slab | 9/8/2022 | Partial Approval | MATTHEW NELSON |
| Smoke Detectors | 9/8/2022 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 11/8/2022 | Approved | MATTHEW NELSON |
| Final | 11/8/2022 | OK to Issue CofO | MATTHEW NELSON |
| Footing/Foundation/Slab | 11/8/2022 | Approved | MATTHEW NELSON |