7406 W 82ND ST 90045
Certificate Information: 7406 W 82ND ST 90045
- Application / Permit
- 22014-20000-00298
- Plan Check / Job No.
- B22VN01096
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 15'11" X 24'6" IRR.-SHAPED ADDITION TO FRONT OF (E) SFD, ADD 3' 6" X 6' 6" FRONT PORCH AND REMODEL (E) SFD TO ADD MASTER BATHROOM/CLOSET, REMODEL KITCHEN AND EXTEND LIVING AREA TO INCLUDE FAMILY ROOM. ALL WORK DONE PER ENGINEERING.
- Permit Issued
- Issued on 4/7/2022
- Issuing Office
- Current Status
- CofO Issued on 11/15/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/24/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/4/2022 | GURUNATH NESARAJAH |
| Corrections Issued | 2/5/2022 | GURUNATH NESARAJAH |
| Applicant returned to address corrections | 3/15/2022 | GURUNATH NESARAJAH |
| Plan Check Approved | 3/25/2022 | GURUNATH NESARAJAH |
| Building Plans Picked Up | 3/30/2022 | APPLICANT |
| Issued | 4/7/2022 | APPLICANT |
| CofO in Progress | 11/9/2022 | BOBBY KEY |
| Permit Finaled | 11/15/2022 | DANIEL ORRANTE |
| CofO Issued | 11/15/2022 | DANIEL ORRANTE |
| Permit Finaled | 11/15/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 2/11/2022 | VASIL MIHALEV |
| Specific Plan | Cleared | 2/16/2022 | LAUREN PADICK |
| Specific Plan | Cleared | 3/2/2022 | FREDDY GARCIA |
| Eng Process Fee Ord 176,300 | Cleared | 3/18/2022 | SAUL GARCIA |
| Roof/Waste drainage to street | Cleared | 3/18/2022 | SAUL GARCIA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Wassef,, Mena Maher Salama; Lic. No.: C84979 | 28131 VALERIO CT VALENCIA, CA 91354 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/2/2022 | Conditional Approval | JESUS RODRIGUEZ |
| Pre-Inspection | 5/2/2022 | Partial Approval | RICHARD STEINBACH |
| PLUMBING-Rough | 6/3/2022 | Corrections Issued | BOBBY KEY |
| PLUMBING-Rough | 6/7/2022 | Partial Approval | BOBBY KEY |
| PLUMBING-Rough | 6/9/2022 | Approved | BOBBY KEY |
| Special/Order Compliance | 6/9/2022 | Approved | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 6/22/2022 | Partial Approval | BOBBY KEY |
| Footing/Foundation/Slab | 6/22/2022 | Approved | BOBBY KEY |
| ELECTRICAL-Rough | 6/28/2022 | Approved | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 7/6/2022 | Corrections Issued | STEPHANIE SWANSON |
| HVAC-Rough | 7/6/2022 | Corrections Issued | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 7/13/2022 | Conditional Approval | JESUS RODRIGUEZ |
| HVAC-Rough | 7/13/2022 | Approved | JESUS RODRIGUEZ |
| Wood Frame | 7/13/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 7/15/2022 | Partial Approval | HERBERT GIRON |
| BUILDING-Rough-Frame | 7/21/2022 | Approved | CLAYTON GRAHAM |
| Green Building Rough | 7/21/2022 | Approved | CLAYTON GRAHAM |
| Interior/Exterior Lathing | 7/21/2022 | Approved | CLAYTON GRAHAM |
| Insulation | 7/27/2022 | Approved | BOBBY KEY |
| Shower Pan | 7/27/2022 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 8/1/2022 | Approved | BOBBY KEY |
| Drywall Nailing | 8/10/2022 | Approved | BOBBY KEY |
| Final | 8/10/2022 | Corrections Issued | BOBBY KEY |
| ELECTRICAL-Final | 10/13/2022 | Corrections Issued | BOBBY KEY |
| Final | 10/13/2022 | Corrections Issued | BOBBY KEY |
| Gas Test | 10/13/2022 | Not Ready for Inspection | BOBBY KEY |
| Green Building Final | 10/13/2022 | Approved | BOBBY KEY |
| HVAC-Final | 10/13/2022 | Corrections Issued | BOBBY KEY |
| PLUMBING-Final | 10/13/2022 | Corrections Issued | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 10/13/2022 | SGSOV Approved | BOBBY KEY |
| Smoke Detectors | 10/13/2022 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 10/26/2022 | Approved | BOBBY KEY |
| Final | 10/26/2022 | Not Ready for Inspection | BOBBY KEY |
| Gas Test | 10/26/2022 | Not Ready for Inspection | BOBBY KEY |
| HVAC-Final | 10/26/2022 | Approved | BOBBY KEY |
| PLUMBING-Final | 10/26/2022 | Not Ready for Inspection | BOBBY KEY |
| Service/Power Release | 10/26/2022 | Not Ready for Inspection | BOBBY KEY |
| ELECTRICAL-Final | 11/4/2022 | Approved | ANDREW NAVE |
| Final | 11/4/2022 | Not Ready for Inspection | ANDREW NAVE |
| Gas Test | 11/4/2022 | Corrections Issued | ANDREW NAVE |
| HVAC-Final | 11/4/2022 | Approved | ANDREW NAVE |
| PLUMBING-Final | 11/4/2022 | Not Ready for Inspection | ANDREW NAVE |
| Service/Power Release | 11/4/2022 | Not Ready for Inspection | ANDREW NAVE |
| Final | 11/9/2022 | OK to Issue CofO | BOBBY KEY |
| Gas Test | 11/9/2022 | Approved | BOBBY KEY |
| PLUMBING-Final | 11/9/2022 | Approved | BOBBY KEY |
| Service/Power Release | 11/9/2022 | Approved | BOBBY KEY |