4970 N BREWSTER DR 91356
Certificate Information: 4970 N BREWSTER DR 91356
- Application / Permit
- 22014-20000-00290
- Plan Check / Job No.
- B22VN01068
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- DEMO ALL EXT AND ITR WALLS EXCEPT 2 WALLS AND ERECT AN IRR SHAPED 73'-9" x 72'-6" TWO-STORY SINGLE FAMILY DWELLING W/ ATT. GARAGE AND OPEN TRELLIS; AUTOMATIC SPRINKLER SYSTEM IS REQ'D
- Permit Issued
- Issued on 5/26/2022
- Issuing Office
- Current Status
- CofO Issued on 5/31/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/24/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/10/2022 | SEAN SHAHMIRI |
| Corrections Issued | 2/14/2022 | SEAN SHAHMIRI |
| Quality Review Completed | 2/17/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 2/18/2022 | APPLICANT |
| Applicant returned to address corrections | 3/8/2022 | SEAN SHAHMIRI |
| Applicant returned to address corrections | 5/9/2022 | SEAN SHAHMIRI |
| Plan Check Approved | 5/9/2022 | SEAN SHAHMIRI |
| Issued | 5/26/2022 | APPLICANT |
| CofO in Progress | 12/29/2023 | SEAN HAUPT |
| No Progress | 2/12/2024 | SEAN WIRCH |
| CofO Issued | 5/31/2024 | JOHN JANSON |
| Permit Finaled | 5/31/2024 | JOHN JANSON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/15/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 2/15/2022 | DAGOVERTO GUERRERO |
| Low Impact Development | Cleared | 4/13/2022 | CHRIS VONG |
| Roof/Waste drainage to street | Cleared | 4/14/2022 | ABHIMAN HENNADIGE |
| Hydrant and Access approval | Cleared | 5/6/2022 | RUEL COLE |
Contact Information
| Contractor | D H R Builders Inc; Lic. No.: 1054047-B | 18336 DELANO STREET TARZANA, CA 91335 |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21243 VENTURA BLVD SUITE 119 WOODLAND HILLS, CA 91364 |
Inspector Information
| JOHN KIDWELL, (818) 774-4314 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 7/14/2022 | Partial Approval | VINCENT HANLEY |
| Underground Mechanical | 7/14/2022 | Partial Approval | VINCENT HANLEY |
| Excavation/Setback/Form/Re-Bar | 7/20/2022 | Partial Approval | ROBERT GOLD |
| Footing/Foundation/Slab | 7/20/2022 | Partial Approval | ROBERT GOLD |
| Deputy Steel/Welding | 8/1/2022 | Conditional Approval | DAVID SANDOVAL |
| Deputy Drilled-In Anchors | 8/9/2022 | Conditional Approval | DAVID SANDOVAL |
| Floor/Roof Diaphrgm/Shear Wall | 8/9/2022 | Partial Approval | DAVID SANDOVAL |
| Deputy Steel/Welding | 8/17/2022 | Conditional Approval | DAVID SANDOVAL |
| Deputy Wood Construction | 8/22/2022 | Conditional Approval | DAVID SANDOVAL |
| Floor/Roof Diaphrgm/Shear Wall | 8/23/2022 | Partial Approval | DAVID SANDOVAL |
| ELECTRICAL-Rough | 10/6/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| Floor/Roof Diaphrgm/Shear Wall | 10/6/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| HVAC-Rough | 10/6/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| PLUMBING-Rough | 10/6/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| Deputy Wood Construction | 10/19/2022 | Approved | DAVID SANDOVAL |
| Floor/Roof Diaphrgm/Shear Wall | 10/19/2022 | Approved | DAVID SANDOVAL |
| PLUMBING-Rough | 10/19/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| Sewer | 10/19/2022 | Approved | DAVID SANDOVAL |
| HVAC-Rough | 10/24/2022 | Approved | DAVID SANDOVAL |
| PLUMBING-Rough | 10/24/2022 | Approved | DAVID SANDOVAL |
| ELECTRICAL-Rough | 11/4/2022 | Approved | PETER FOLLING |
| Interior/Exterior Lathing | 11/4/2022 | Partial Approval | PETER FOLLING |
| Shower Pan | 11/4/2022 | Approved | PETER FOLLING |
| Interior/Exterior Lathing | 11/15/2022 | Approved | DAVID SANDOVAL |
| Green Building Rough | 12/1/2022 | Approved | DAVID SANDOVAL |
| Insulation | 12/1/2022 | Approved | DAVID SANDOVAL |
| Drywall Nailing | 12/8/2022 | Approved | JESUS PINEDA |
| Insulation | 12/8/2022 | Partial Inspection | JESUS PINEDA |
| BUILDING-Rough-Frame | 10/19/2023 | Approved | SEAN HAUPT |
| Final | 10/19/2023 | Corrections Issued | SEAN HAUPT |
| Footing/Foundation/Slab | 10/19/2023 | Approved | SEAN HAUPT |
| Green Building Final | 10/19/2023 | Approved | SEAN HAUPT |
| SGSOV-Seismic Gas S/O Valve | 10/19/2023 | SGSOV Approved | SEAN HAUPT |
| Service/Power Release | 10/19/2023 | Not Ready for Inspection | SEAN HAUPT |
| Smoke Detectors | 10/19/2023 | Approved | SEAN HAUPT |
| Service/Power Release | 11/2/2023 | Approved | SEAN HAUPT |
| Final | 12/28/2023 | OK to Issue CofO | SEAN HAUPT |