1937 S 7TH AVE 90018
Certificate Information: 1937 S 7TH AVE 90018
- Application / Permit
- 22014-20000-00279
- Plan Check / Job No.
- B22VN01044
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE AND (N) 33'-6" X 32'-2" IRREG SHAPED ADDITION TO (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d).
- Permit Issued
- Issued on 3/21/2025
- Issuing Office
- Current Status
- Issued on 3/21/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/30/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/10/2022 | LUISANGEL VALENZUELA |
| Corrections Issued | 2/12/2022 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 3/20/2024 | ISIS ARGUETA |
| Applicant returned to address corrections | 7/26/2024 | KAMYAR EMAMI |
| Plan Check Approved | 3/21/2025 | YAQUB MIRZA |
| Issued | 3/21/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 4/28/2022 | AMAAN MALIK |
| Eng Process Fee Ord 176,300 | Cleared | 5/13/2022 | AMAAN MALIK |
| Sewer availability | Cleared | 5/13/2022 | AMAAN MALIK |
| Roof/Waste drainage to street | Cleared | 3/26/2024 | JEANIE LAM |
| Community Plan Implem. Overlay | Cleared | 6/26/2024 | KYLE WINSTON |
| Construction near power lines | Cleared | 11/9/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 9/16/2025 | Approved | ALEX COLIN |
| Deputy Drilled-In Anchors | 9/22/2025 | Conditional Approval | JUSTIN HAWLEY |
| Footing/Foundation/Slab | 9/26/2025 | Approved | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 11/13/2025 | Approved | JUSTIN HAWLEY |
| Floor/Roof Diaphrgm/Shear Wall | 11/13/2025 | Approved | JUSTIN HAWLEY |
| Rough-Elec/Plmb/HVAC | 11/13/2025 | Approved | JUSTIN HAWLEY |
| Special/Order Compliance | 11/13/2025 | Corrections Issued | JUSTIN HAWLEY |
| Insulation | 12/18/2025 | Corrections Issued | DEVON JACKSON |
| Interior/Exterior Lathing | 12/18/2025 | Partial Approval | DEVON JACKSON |
| Shower Pan | 12/18/2025 | Approved | DEVON JACKSON |
| Drywall Nailing | 1/9/2026 | Approved | JUSTIN HAWLEY |
| Green Building Rough | 1/9/2026 | Approved | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 1/9/2026 | Approved | JUSTIN HAWLEY |