23717 W ARMINTA ST 91304

Certificate Information: 23717 W ARMINTA ST 91304

Application / Permit
22014-20000-00267
Plan Check / Job No.
B22VN00993
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
1ST AND 2ND FLOOR ADDITION TO (E) 2-STORY SFD WITH ATTACHED GARAGE.
Permit Issued
Issued on 6/28/2022
Issuing Office
Metro
Current Status
CofO Issued on 5/30/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/24/2022 APPLICANT
Assigned to Plan Check Engineer 2/24/2022 MAHNAZ NOURHASHEMI
Corrections Issued 3/3/2022 MAHNAZ NOURHASHEMI
Quality Review Completed 3/11/2022 TEODORO DIAZ RODRIGUEZ
Building Plans Picked Up 6/22/2022 APPLICANT
Plan Check Approved 6/28/2022 MAHNAZ NOURHASHEMI
Issued 6/28/2022 APPLICANT
CofO in Progress 4/21/2023 CHRIS CHRISTENSEN
CofO Issued 5/30/2023 JOHN JANSON
Permit Finaled 5/30/2023 JOHN JANSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/25/2022 DAGOVERTO GUERRERO
Sewer availability Cleared 3/25/2022 DAGOVERTO GUERRERO
Grading Pre-Inspection Cleared 4/28/2022 KIRK LINKLATER
Low Impact Development Cleared 6/6/2022 MARCO SANCHEZ
Roof/Waste drainage to street Cleared 6/9/2022 JOSE DUARTE-DIAZ
GPI Written Notices Cleared 6/28/2022 MAHNAZ NOURHASHEMI

Contact Information

Contractor Adar Builders Inc; Lic. No.: 1051859-B 7659 LOUISE AVE      NORTHRIDGE, CA 91325
Engineer Almalla,, Dean; Lic. No.: C58024 15053 VENTURA BLVD STE 205      SHERMAN OAKS, CA 91403

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 8/12/2022 Conditional Approval CHRIS CHRISTENSEN
Excavation/Setback/Form/Re-Bar 8/17/2022 Approved CHRIS CHRISTENSEN
PLUMBING-Rough 8/17/2022 Partial Approval CHRIS CHRISTENSEN
ELECTRICAL-Rough 10/11/2022 Approved CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 10/11/2022 Partial Approval CHRIS CHRISTENSEN
HVAC-Rough 10/11/2022 Corrections Issued CHRIS CHRISTENSEN
PLUMBING-Rough 10/11/2022 Corrections Issued CHRIS CHRISTENSEN
Wood Frame 10/11/2022 Corrections Issued CHRIS CHRISTENSEN
Deputy Wood Construction 10/12/2022 Conditional Approval CHRIS CHRISTENSEN
BUILDING-Rough-Frame 10/20/2022 Conditional Approval CHRIS CHRISTENSEN
ELECTRICAL-Rough 10/20/2022 Approved CHRIS CHRISTENSEN
Green Building Rough 10/20/2022 Approved CHRIS CHRISTENSEN
HVAC-Rough 10/20/2022 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 10/20/2022 Partial Approval CHRIS CHRISTENSEN
PLUMBING-Rough 10/20/2022 Approved CHRIS CHRISTENSEN
Insulation 10/28/2022 Not Ready for Inspection CHRIS CHRISTENSEN
Interior/Exterior Lathing 10/28/2022 Not Ready for Inspection CHRIS CHRISTENSEN
Insulation 11/8/2022 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 11/8/2022 Partial Approval CHRIS CHRISTENSEN
Drywall Nailing 12/2/2022 Approved JUSTIN HAWLEY
BUILDING-Rough-Frame 4/5/2023 Approved CHRIS CHRISTENSEN
ELECTRICAL-Final 4/5/2023 Approved CHRIS CHRISTENSEN
Final 4/5/2023 Corrections Issued CHRIS CHRISTENSEN
Footing/Foundation/Slab 4/5/2023 Approved CHRIS CHRISTENSEN
Green Building Final 4/5/2023 Approved CHRIS CHRISTENSEN
HVAC-Final 4/5/2023 Approved CHRIS CHRISTENSEN
PLUMBING-Final 4/5/2023 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 4/5/2023 SGSOV Approved CHRIS CHRISTENSEN
Smoke Detectors 4/5/2023 Approved CHRIS CHRISTENSEN
Final 4/20/2023 OK to Issue CofO CHRIS CHRISTENSEN