234 N AVENUE 59 90042

Certificate Information: 234 N AVENUE 59 90042

Application / Permit
22014-20000-00246
Plan Check / Job No.
B22VN00934
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT DETACHED GARAGE WITH ADDITION ( 18' X 12' ) INTO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c) AND (d). WORK PER WFPP.
Permit Issued
Issued on 8/2/2022
Issuing Office
Valley
Current Status
CofO Issued on 10/14/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/20/2022 APPLICANT
Assigned to Plan Check Engineer 2/2/2022 ROSENDO MEDINA
Corrections Issued 2/5/2022 ROSENDO MEDINA
Plan Check Approved 7/25/2022 ROSENDO MEDINA
Building Plans Picked Up 7/26/2022 APPLICANT
Issued 8/2/2022 APPLICANT
CofO in Progress 10/4/2023 ROY SPAULDING
Permit Finaled 10/14/2023 DEROLD HAUFF
CofO Issued 10/14/2023 DEROLD HAUFF
Permit Finaled 10/14/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 2/10/2022 WALLIE JONG
Roof/Waste drainage to street Cleared 2/10/2022 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 2/11/2022 WALLIE JONG
Sewer availability Cleared 2/11/2022 WALLIE JONG
HPOZ Cleared 2/25/2022 KATIE DEBIASE
ZI Cleared 2/25/2022 KATIE DEBIASE
Grading Pre-Inspection Cleared 3/7/2022 ALEXANDER HELFER
Specific Plan Cleared 7/14/2022 NICOLE SANCHEZ
ZI Cleared 7/14/2022 NICOLE SANCHEZ

Contact Information

No Data Available.

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/9/2022 Approved OSVALDO PARAMO
Footing/Foundation/Slab 9/9/2022 Approved OSVALDO PARAMO
PLUMBING-Rough 9/9/2022 Partial Approval OSVALDO PARAMO
BUILDING-Rough-Frame 10/24/2022 Corrections Issued SCOTT FINNILA
ELECTRICAL-Rough 10/24/2022 Corrections Issued SCOTT FINNILA
Green Building Rough 10/24/2022 Corrections Issued SCOTT FINNILA
PLUMBING-Rough 10/24/2022 Corrections Issued SCOTT FINNILA
Underground Mechanical 10/24/2022 Partial Approval SCOTT FINNILA
BUILDING-Rough-Frame 10/28/2022 Not Ready for Inspection CRAIG VAUGHAN
ELECTRICAL-Rough 10/28/2022 Not Ready for Inspection CRAIG VAUGHAN
Green Building Rough 10/28/2022 Not Ready for Inspection CRAIG VAUGHAN
PLUMBING-Rough 10/28/2022 Not Ready for Inspection CRAIG VAUGHAN
Underground Mechanical 10/28/2022 Not Ready for Inspection CRAIG VAUGHAN
BUILDING-Rough-Frame 11/2/2022 Partial Approval CRAIG VAUGHAN
ELECTRICAL-Rough 11/2/2022 Not Ready for Inspection CRAIG VAUGHAN
PLUMBING-Rough 11/2/2022 Approved CRAIG VAUGHAN
Underground Mechanical 11/2/2022 Approved CRAIG VAUGHAN
ELECTRICAL-Rough 11/18/2022 Approved OSVALDO PARAMO
Interior/Exterior Lathing 11/18/2022 Partial Approval OSVALDO PARAMO
BUILDING-Rough-Frame 11/23/2022 Approved CRAIG VAUGHAN
Green Building Rough 11/23/2022 Approved CRAIG VAUGHAN
HVAC-Rough 11/23/2022 Partial Approval CRAIG VAUGHAN
Insulation 11/30/2022 Approved KATHRYN BUTTERWORTH
Shower Pan 11/30/2022 Approved KATHRYN BUTTERWORTH
Drywall Nailing 12/7/2022 Approved AMY COLIN
Final 8/16/2023 Corrections Issued CRAIG VAUGHAN
Green Building Final 8/16/2023 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 8/16/2023 SGSOV Not Ready CRAIG VAUGHAN
Smoke Detectors 8/16/2023 Approved CRAIG VAUGHAN
Final 9/21/2023 Corrections Issued CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 9/21/2023 SGSOV Approved CRAIG VAUGHAN
Final 10/2/2023 Corrections Issued ROY SPAULDING
Final 10/3/2023 OK to Issue CofO ROY SPAULDING
Service/Power Release 10/3/2023 Approved ROY SPAULDING