5749 N COLUMBUS AVE 91411
Certificate Information: 5749 N COLUMBUS AVE 91411
- Application / Permit
- 22014-20000-00240
- Plan Check / Job No.
- B22VN00910
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 10'x15' PATIO COVER, 17'x27' ADDITION, AND SFD INTERIOR REMODEL
- Permit Issued
- Issued on 4/13/2022
- Issuing Office
- Current Status
- CofO Issued on 5/7/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/20/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/2/2022 | JESSE ARELLANO |
| Corrections Issued | 2/2/2022 | JESSE ARELLANO |
| Applicant returned to address corrections | 3/15/2022 | JESSE ARELLANO |
| Plan Check Approved | 4/1/2022 | JESSE ARELLANO |
| Building Plans Picked Up | 4/4/2022 | APPLICANT |
| Issued | 4/13/2022 | APPLICANT |
| CofO in Progress | 5/2/2023 | RYAN SALAZAR |
| Permit Finaled | 5/7/2023 | DEROLD HAUFF |
| CofO Issued | 5/7/2023 | DEROLD HAUFF |
| Permit Finaled | 5/7/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/25/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 2/25/2022 | DAGOVERTO GUERRERO |
| Low Impact Development | Cleared | 3/2/2022 | KHAING AYE |
| Roof/Waste drainage to street | Cleared | 3/3/2022 | DAGOVERTO GUERRERO |
| Green Code | Cleared | 4/1/2022 | JESSE ARELLANO |
Contact Information
| Contractor | Knudsen Mark Curtis; Lic. No.: 544786-B | 22639 MIRANDA ST WOODLAND HILLS, CA 91367 |
| Engineer | Pall,, Avtar S; Lic. No.: S4333 | 22115 MICHALE ST WEST HILLS, CA 91304 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/15/2022 | Conditional Approval | MICHAEL TEMPLE |
| Footing/Foundation/Slab | 4/18/2022 | Approved | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 4/25/2022 | Partial Approval | JENNIFER RABUCHIN |
| Green Building Rough | 4/25/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Insulation | 4/25/2022 | Partial Approval | JENNIFER RABUCHIN |
| MERV13>=Rough | 4/25/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| PLUMBING-Rough | 4/25/2022 | Partial Approval | JENNIFER RABUCHIN |
| Deputy Wood Construction | 5/3/2022 | Conditional Approval | ALAN MORELOS |
| BUILDING-Rough-Frame | 5/9/2022 | Approved | RICHARD DOCKUS |
| ELECTRICAL-Rough | 5/9/2022 | Approved | RICHARD DOCKUS |
| Green Building Rough | 5/9/2022 | Approved | RICHARD DOCKUS |
| MERV13>=Rough | 5/9/2022 | Approved | RICHARD DOCKUS |
| PLUMBING-Rough | 5/9/2022 | Approved | RICHARD DOCKUS |
| Insulation | 5/13/2022 | Approved | DEANDRE HOFFMAN |
| Interior/Exterior Lathing | 5/13/2022 | Partial Approval | DEANDRE HOFFMAN |
| Drywall Nailing | 5/20/2022 | Approved | ALAN MORELOS |
| Interior/Exterior Lathing | 5/20/2022 | Approved | ALAN MORELOS |
| Final | 5/1/2023 | OK to Issue CofO | RYAN SALAZAR |
| Green Building Final | 5/1/2023 | Approved | RYAN SALAZAR |
| MERV13>=Final | 5/1/2023 | Approved | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 5/1/2023 | SGSOV Approved | RYAN SALAZAR |
| Smoke Detectors | 5/1/2023 | Approved | RYAN SALAZAR |