10623 W PAWNEE ST 91352
Certificate Information: 10623 W PAWNEE ST 91352
- Application / Permit
- 22014-20000-00238
- Plan Check / Job No.
- B22VN00905
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 18'-2" X 20'-2" DETACHED GARAGE AND ADD 20'-2" X 23'-2" INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER WFPP.
- Permit Issued
- Issued on 4/28/2022
- Issuing Office
- Current Status
- CofO Issued on 3/17/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/20/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/31/2022 | RAPHAEL ROSAS |
| Corrections Issued | 1/31/2022 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 3/28/2022 | RAPHAEL ROSAS |
| Plan Check Approved | 4/8/2022 | RAPHAEL ROSAS |
| Building Plans Picked Up | 4/12/2022 | APPLICANT |
| Issued | 4/28/2022 | APPLICANT |
| CofO in Progress | 2/22/2023 | DAVID ANDERSON |
| Permit Finaled | 3/17/2023 | MICHAEL SMITH |
| CofO Issued | 3/17/2023 | MICHAEL SMITH |
| Permit Finaled | 3/17/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 2/2/2022 | JARED ABEGG |
| Roof/Waste drainage to street | Cleared | 2/2/2022 | JARED ABEGG |
| Sewer availability | Cleared | 2/8/2022 | JARED ABEGG |
| Construction near power lines | Cleared | 3/28/2022 | WALTER RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 4/27/2022 | JARED ABEGG |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| DAVID ANDERSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/27/2022 | Conditional Approval | DAVID ANDERSON |
| Deputy Drilled-In Anchors | 6/28/2022 | Approved | DAVID ANDERSON |
| PLUMBING-Rough | 6/30/2022 | Approved | DAVID ANDERSON |
| Footing/Foundation/Slab | 7/8/2022 | Approved | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 7/28/2022 | Approved | DAVID ANDERSON |
| ELECTRICAL-Rough | 8/19/2022 | Approved | DAVID ANDERSON |
| HVAC-Rough | 8/19/2022 | Approved | DAVID ANDERSON |
| PLUMBING-Rough | 8/19/2022 | Approved | DAVID ANDERSON |
| Insulation | 8/26/2022 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 8/26/2022 | Approved | DAVID ANDERSON |
| Drywall Nailing | 9/1/2022 | No Access for Inspection | DAVID ANDERSON |
| Drywall Nailing | 9/7/2022 | Approved | DAVID ANDERSON |
| Excavation/Setback/Form/Re-Bar | 9/12/2022 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 9/12/2022 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 9/19/2022 | Approved | DAVID ANDERSON |
| Shower Pan | 9/19/2022 | Approved | DAVID ANDERSON |
| Sewer | 11/29/2022 | Approved | DAVID ANDERSON |
| Underground Mechanical | 11/29/2022 | Approved | DAVID ANDERSON |
| BUILDING-Rough-Frame | 2/14/2023 | Approved | DAVID ANDERSON |
| Final | 2/14/2023 | Corrections Issued | DAVID ANDERSON |
| Green Building Final | 2/14/2023 | Approved | DAVID ANDERSON |
| Green Building Rough | 2/14/2023 | Approved | DAVID ANDERSON |
| MERV13>=Final | 2/14/2023 | Approved | DAVID ANDERSON |
| MERV13>=Rough | 2/14/2023 | Approved | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 2/14/2023 | SGSOV Not Ready | DAVID ANDERSON |
| Smoke Detectors | 2/14/2023 | Approved | DAVID ANDERSON |
| Final | 2/21/2023 | OK to Issue CofO | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 2/21/2023 | SGSOV Approved | DAVID ANDERSON |