10962 W PENROSE ST 91352
Certificate Information: 10962 W PENROSE ST 91352
- Application / Permit
- 22014-20000-00231
- Plan Check / Job No.
- B22VN00869
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 688 SQ. FT. ADDITION TO AND CONVERT THE (E) 240 SQ. FT. SHED INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d).
- Permit Issued
- Issued on 4/22/2022
- Issuing Office
- Current Status
- CofO Issued on 3/22/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/20/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/2/2022 | JESSE ARELLANO |
| Corrections Issued | 2/3/2022 | JESSE ARELLANO |
| Plan Check Approved | 4/14/2022 | JESSE ARELLANO |
| Issued | 4/22/2022 | APPLICANT |
| Building Plans Picked Up | 4/28/2022 | APPLICANT |
| CofO in Progress | 1/10/2024 | DAVID ANDERSON |
| Permit Finaled | 3/22/2024 | RUBEN SALAS |
| CofO Issued | 3/22/2024 | RUBEN SALAS |
| Permit Finaled | 3/22/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 3/8/2022 | AMIR KASHFI |
| Sewer availability | Cleared | 3/8/2022 | AMIR KASHFI |
| Eng Process Fee Ord 176,300 | Cleared | 3/10/2022 | AMIR KASHFI |
| Low Impact Development | Cleared | 3/21/2022 | TA ANH |
| Roof/Waste drainage to street | Cleared | 4/5/2022 | DAGOVERTO GUERRERO |
| Green Code | Cleared | 4/14/2022 | JESSE ARELLANO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Adzhemyan,, Arsen; Lic. No.: C89103 | 1010 RALEIGH ST APT 107 GLENDALE, CA 91205 |
Inspector Information
| DAVID ANDERSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/5/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Pre-Inspection | 5/24/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Pre-Inspection | 8/14/2023 | Approved | DAVID ANDERSON |
| Pre-Inspection | 9/26/2023 | Approved | DAVID ANDERSON |
| Pre-Inspection | 9/28/2023 | Approved | DAVID ANDERSON |
| BUILDING-Rough-Frame | 11/6/2023 | Approved | DAVID ANDERSON |
| Footing/Foundation/Slab | 11/6/2023 | Approved | DAVID ANDERSON |
| Green Building Rough | 11/6/2023 | Approved | DAVID ANDERSON |
| Rough-Elec/Plmb/HVAC | 11/6/2023 | Approved | DAVID ANDERSON |
| Insulation | 11/28/2023 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 11/28/2023 | Approved | DAVID ANDERSON |
| Drywall Nailing | 12/1/2023 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 12/1/2023 | Approved | DAVID ANDERSON |
| Final | 1/9/2024 | OK to Issue CofO | DAVID ANDERSON |
| Green Building Final | 1/9/2024 | Approved | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 1/9/2024 | SGSOV Approved | DAVID ANDERSON |
| Smoke Detectors | 1/9/2024 | Approved | DAVID ANDERSON |