19016 W KESWICK ST 91335
Certificate Information: 19016 W KESWICK ST 91335
- Application / Permit
- 22014-20000-00221
- Plan Check / Job No.
- B22VN00812
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION TO (E) SINGLE FAMILY DWELLING WITH OPEN TRELLIS. BUILDING TO BE EQUIPPED WITH AUTOMATIC SPRINKLERS SYSTEM PER NFPA-13D.
- Permit Issued
- Issued on 11/28/2023
- Issuing Office
- Current Status
- CofO in Progress on 6/5/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/19/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/10/2022 | ARMEN JIVALAGIAN |
| Corrections Issued | 2/16/2022 | ARMEN JIVALAGIAN |
| Quality Review Completed | 2/24/2022 | KEN GILL |
| Building Plans Picked Up | 3/4/2022 | APPLICANT |
| Applicant returned to address corrections | 11/22/2022 | ARMEN JIVALAGIAN |
| Applicant returned to address corrections | 7/20/2023 | ARMEN JIVALAGIAN |
| Plan Check Approved | 11/7/2023 | ARMEN JIVALAGIAN |
| Issued | 11/28/2023 | APPLICANT |
| CofO in Progress | 6/5/2025 | JUAN ALVARADO |
| CofO in Progress | 6/5/2025 | ROBERT GOLD |
Permit Application Clearance Information
| Permit | Cleared | 5/12/2022 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 5/17/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 5/20/2022 | DAGOVERTO GUERRERO |
| Hydrant and Access approval | Cleared | 10/14/2022 | GILBERT URREA |
| Low Impact Development | Cleared | 10/17/2022 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 10/18/2022 | DAGOVERTO GUERRERO |
| ZI | Cleared | 10/19/2022 | ASHLEY RODARTE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/13/2024 | Approved | JEFFREY BULL |
| Special/Order Compliance | 4/3/2024 | Approved | JEFFREY BULL |
| Pre-Inspection | 4/18/2024 | Approved | JEFFREY BULL |
| PLUMBING-Rough | 5/2/2024 | Partial Approval | JEFFREY BULL |
| Excavation/Setback/Form/Re-Bar | 5/7/2024 | Approved | JEFFREY BULL |
| BUILDING-Rough-Frame | 7/18/2024 | Not Ready for Inspection | JEFFREY BULL |
| ELECTRICAL-Rough | 7/18/2024 | Approved | JEFFREY BULL |
| Green Building Rough | 7/18/2024 | Not Ready for Inspection | JEFFREY BULL |
| HVAC-Rough | 7/18/2024 | Not Ready for Inspection | JEFFREY BULL |
| PLUMBING-Rough | 7/18/2024 | Approved | JEFFREY BULL |
| Deputy Wood Construction | 7/22/2024 | Conditional Approval | JEFFREY BULL |
| BUILDING-Rough-Frame | 9/16/2024 | Approved | JEFFREY BULL |
| Green Building Rough | 9/16/2024 | Approved | JEFFREY BULL |
| Insulation | 9/24/2024 | Corrections Issued | SCOTT SOBEL |
| Drywall Nailing | 9/30/2024 | Approved | JEFFREY BULL |
| Final | 4/16/2025 | Corrections Issued | JUAN ALVARADO |
| Footing/Foundation/Slab | 4/16/2025 | Approved | JUAN ALVARADO |
| Green Building Final | 4/16/2025 | Approved | JUAN ALVARADO |
| SGSOV-Seismic Gas S/O Valve | 4/16/2025 | SGSOV Not Ready | JUAN ALVARADO |
| Smoke Detectors | 4/16/2025 | Approved | JUAN ALVARADO |
| Final | 5/16/2025 | Not Ready for Inspection | JUAN ALVARADO |
| SGSOV-Seismic Gas S/O Valve | 5/16/2025 | SGSOV Approved | JUAN ALVARADO |
| Final | 5/23/2025 | Corrections Issued | ARUTYUN MADATYAN |
| ELECTRICAL-Final | 6/4/2025 | Approved | JUAN ALVARADO |
| Final | 6/4/2025 | Partial Approval | JUAN ALVARADO |
| HVAC-Final | 6/4/2025 | Approved | JUAN ALVARADO |
| PLUMBING-Final | 6/4/2025 | Approved | JUAN ALVARADO |
| Final | 6/12/2026 | Corrections Issued | JUAN ALVARADO |