13408 W HERRON ST 1 91342

Certificate Information: 13408 W HERRON ST 1 91342

Application / Permit
22014-20000-00208
Plan Check / Job No.
B22VN00795
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan Proposed (N) addition (103.5 sq. ft.) TO (E) SFD
Permit Issued
Issued on 2/10/2022
Issuing Office
Current Status
CofO Issued on 3/6/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/25/2022 APPLICANT
Assigned to Plan Check Engineer 1/26/2022 ARSALAN SHABESTARI
Corrections Issued 1/26/2022 ARSALAN SHABESTARI
Plan Check Approved 2/4/2022 ARSALAN SHABESTARI
Issued 2/10/2022 APPLICANT
CofO in Progress 12/13/2023 KEVIN BERBERYAN
Permit Finaled 3/6/2024 RUBEN SALAS
CofO Issued 3/6/2024 RUBEN SALAS
Permit Finaled 3/6/2024 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/27/2022 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 1/27/2022 CARLOS AGUILERA
Sewer availability Cleared 1/27/2022 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/6/2023 Partial Approval MATTHEW NELSON
Footing/Foundation/Slab 3/6/2023 Partial Approval MATTHEW NELSON
Sewer 3/6/2023 Not Ready for Inspection MATTHEW NELSON
Underground Mechanical 3/6/2023 Partial Approval MATTHEW NELSON
Deputy Other (see comments) 3/14/2023 Conditional Approval MICHAEL SMITH
Footing/Foundation/Slab 4/7/2023 Approved ARAM AVEDISIAN
Sewer 4/7/2023 Approved ARAM AVEDISIAN
Deputy Other (see comments) 4/12/2023 Conditional Approval MICHAEL SMITH
BUILDING-Rough-Frame 5/22/2023 Partial Approval ROBERT GOLD
ELECTRICAL-Rough 5/22/2023 Approved ROBERT GOLD
Floor/Roof Diaphrgm/Shear Wall 5/22/2023 Approved ROBERT GOLD
PLUMBING-Rough 5/22/2023 Partial Approval ROBERT GOLD
Wood Frame 5/22/2023 Not Ready for Inspection ROBERT GOLD
HVAC-Rough 5/31/2023 Corrections Issued CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 5/31/2023 Not Ready for Inspection CHRISTOPHER DELLEFIELD
PLUMBING-Rough 5/31/2023 Approved CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 6/5/2023 Approved CHRISTOPHER DELLEFIELD
HVAC-Rough 6/5/2023 Approved CHRISTOPHER DELLEFIELD
Insulation 6/5/2023 Approved CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 6/5/2023 Approved CHRISTOPHER DELLEFIELD
Drywall Nailing 6/9/2023 Approved MICHEL ABAJAN
Shower Pan 6/9/2023 Approved MICHEL ABAJAN
Special/Order Compliance 6/13/2023 Not Ready for Inspection THOMAS FINNILA
ELECTRICAL-Final 11/15/2023 Approved KEVIN BERBERYAN
Final 11/15/2023 Corrections Issued KEVIN BERBERYAN
PLUMBING-Final 11/15/2023 Approved KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 11/15/2023 SGSOV Not Ready KEVIN BERBERYAN
Smoke Detectors 11/15/2023 Approved KEVIN BERBERYAN
Final 12/11/2023 OK to Issue CofO KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 12/11/2023 SGSOV Approved KEVIN BERBERYAN