6502 N CHARLESWORTH AVE 91606

Certificate Information: 6502 N CHARLESWORTH AVE 91606

Application / Permit
22014-20000-00206
Plan Check / Job No.
B22VN00790
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADD 2-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22A33(c)(d) TO (E) GARAGE
Permit Issued
Issued on 4/24/2023
Issuing Office
Valley
Current Status
CofO Issued on 9/12/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/19/2022 APPLICANT
Assigned to Plan Check Engineer 2/17/2022 NILOOFAR MEHRAIN
Corrections Issued 3/1/2022 NILOOFAR MEHRAIN
Quality Review Completed 3/8/2022 STEVEN KIM
Building Plans Picked Up 3/8/2022 APPLICANT
Plan Check Approved 4/11/2023 NILOOFAR MEHRAIN
Issued 4/24/2023 APPLICANT
CofO in Progress 8/29/2024 OGANES TARAKHCHYAN
CofO Issued 9/12/2024 DANIEL ORRANTE
Permit Finaled 9/12/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 3/10/2022 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 3/18/2022 DAGOVERTO GUERRERO
Sewer availability Cleared 3/18/2022 DAGOVERTO GUERRERO
Hydrant and Access approval Cleared 4/11/2022 LAURINDA MEADE
Low Impact Development Cleared 5/3/2022 SUNG JOON WON
Roof/Waste drainage to street Cleared 5/19/2022 DAGOVERTO GUERRERO
Construction near power lines Cleared 3/24/2023 RIDWAN HARDY
Construction within easement Cleared 3/24/2023 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Manlangit,, Vicente Balingasa; Lic. No.: C75499 7919 SAUSALITO AVE      WEST HILLS, CA 91304

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Gas Test 7/3/2023 Not Ready for Inspection KIRK SANDERS
Sewer 7/3/2023 Approved KIRK SANDERS
Underground Mechanical 7/3/2023 Partial Approval KIRK SANDERS
Footing/Foundation/Slab 7/27/2023 Approved KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 11/29/2023 Partial Approval KIRK SANDERS
Wood Frame 11/29/2023 Not Ready for Inspection KIRK SANDERS
Deputy Wood Construction 12/15/2023 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 1/18/2024 Corrections Issued JOSE AVILA
ELECTRICAL-Rough 1/31/2024 Corrections Issued JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 1/31/2024 Corrections Issued JOSE AVILA
PLUMBING-Rough 1/31/2024 Corrections Issued JOSE AVILA
ELECTRICAL-Rough 2/7/2024 Approved JOSE AVILA
HVAC-Rough 2/7/2024 Approved JOSE AVILA
PLUMBING-Rough 2/7/2024 Approved JOSE AVILA
BUILDING-Rough-Frame 2/23/2024 Corrections Issued KIRK SANDERS
Green Building Rough 2/23/2024 Approved KIRK SANDERS
Interior/Exterior Lathing 2/23/2024 Partial Approval KIRK SANDERS
Shower Pan 2/23/2024 Approved KIRK SANDERS
Insulation 2/28/2024 Approved KIRK SANDERS
Deputy Wood Construction 3/4/2024 Conditional Approval JUAN VALENZUELA
Drywall Nailing 3/8/2024 Partial Approval JOSE AVILA
Interior/Exterior Lathing 3/8/2024 Approved JOSE AVILA
Drywall Nailing 3/12/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 6/21/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Final 6/21/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Green Building Final 6/21/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 6/21/2024 SGSOV Not Ready ROBERTO PALACIOS-LOPEZ
Smoke Detectors 6/21/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Special/Order Compliance 6/21/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Final 7/3/2024 Approved OGANES TARAKHCHYAN
HVAC-Final 7/3/2024 Approved OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 7/3/2024 SGSOV Approved OGANES TARAKHCHYAN
Smoke Detectors 7/3/2024 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 8/5/2024 Approved OGANES TARAKHCHYAN
ELECTRICAL-Final 8/5/2024 Approved OGANES TARAKHCHYAN
Final 8/5/2024 OK to Issue CofO OGANES TARAKHCHYAN
PLUMBING-Final 8/5/2024 Approved OGANES TARAKHCHYAN