2024 N GLENDALE BLVD 90039
Certificate Information: 2024 N GLENDALE BLVD 90039
- Application / Permit
- 22014-20000-00202
- Plan Check / Job No.
- B22VN00782
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 28'-2' X 21'IRREGULAR SHAPED (2) STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e)
- Permit Issued
- Issued on 11/14/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/29/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/19/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/17/2022 | SELLA BENYAMIN |
| Corrections Issued | 2/22/2022 | SELLA BENYAMIN |
| Quality Review Completed | 3/1/2022 | STEVEN KIM |
| Building Plans Picked Up | 4/29/2022 | APPLICANT |
| Applicant returned to address corrections | 10/11/2022 | SELLA BENYAMIN |
| Plan Check Approved | 10/25/2022 | SELLA BENYAMIN |
| Issued | 11/14/2022 | APPLICANT |
| CofO in Progress | 12/19/2023 | THOMAS LOGRASSO |
| No Progress | 12/30/2023 | DEROLD HAUFF |
| CofO in Progress | 1/3/2024 | SCOTT FINNILA |
| No Progress | 1/7/2024 | DEROLD HAUFF |
| CofO in Progress | 1/29/2024 | DEROLD HAUFF |
| Permit Finaled | 1/29/2024 | DEROLD HAUFF |
| CofO Issued | 1/29/2024 | DEROLD HAUFF |
| Permit Finaled | 1/29/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/11/2022 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 8/12/2022 | JEANIE LAM |
| Sewer availability | Cleared | 8/15/2022 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 9/30/2022 | AMAAN MALIK |
| GPI Written Notices | Cleared | 10/25/2022 | SELLA BENYAMIN |
| Grading Pre-Inspection | Cleared | 10/25/2022 | SELLA BENYAMIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Evangelista,, Gil Viernes; Lic. No.: S2422 | 749 N FEATHERWOOD DR DIAMOND BAR, CA 91765 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 2/8/2023 | Partial Approval | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 3/13/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 3/17/2023 | Not Ready for Inspection | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 3/20/2023 | Approved | THOMAS LOGRASSO |
| Special/Order Compliance | 5/19/2023 | Approved | THOMAS LOGRASSO |
| Underground Mechanical | 7/14/2023 | Partial Approval | THOMAS LOGRASSO |
| Rough-Elec/Plmb/HVAC | 7/19/2023 | Corrections Issued | THOMAS LOGRASSO |
| Sewer | 7/19/2023 | Approved | THOMAS LOGRASSO |
| Underground Mechanical | 7/19/2023 | Approved | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 7/27/2023 | Corrections Issued | THOMAS LOGRASSO |
| Green Building Rough | 7/27/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Rough-Elec/Plmb/HVAC | 7/27/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Verify Sprinkler Sign Off | 7/27/2023 | Approved | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 8/17/2023 | Conditional Approval | THOMAS LOGRASSO |
| Insulation | 8/17/2023 | Corrections Issued | THOMAS LOGRASSO |
| Rough-Elec/Plmb/HVAC | 8/17/2023 | Approved | THOMAS LOGRASSO |
| Insulation | 8/21/2023 | Approved | ALIZAH MAYAGOITIA |
| Drywall Nailing | 8/29/2023 | Conditional Approval | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 8/29/2023 | Approved | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 11/29/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Final | 11/29/2023 | Corrections Issued | THOMAS LOGRASSO |
| Green Building Final | 11/29/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Green Building Rough | 11/29/2023 | Approved | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 11/29/2023 | SGSOV Not Ready | THOMAS LOGRASSO |
| Service/Power Release | 11/29/2023 | Not Required | THOMAS LOGRASSO |
| Smoke Detectors | 11/29/2023 | Approved | THOMAS LOGRASSO |
| Final | 12/12/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 12/12/2023 | SGSOV Approved | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 12/18/2023 | Approved | THOMAS LOGRASSO |
| Final | 12/18/2023 | OK to Issue CofO | THOMAS LOGRASSO |
| Green Building Final | 12/18/2023 | Approved | THOMAS LOGRASSO |