4454 E ALUMNI AVE 90041
Certificate Information: 4454 E ALUMNI AVE 90041
- Application / Permit
- 22014-20000-00191
- Plan Check / Job No.
- B22VN00715
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 15'-6" X 16'-6" DETACHED GARAGE AND ADD 13'-8.5" X 17'2.5" INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 4/25/2022
- Issuing Office
- Current Status
- CofO Issued on 1/10/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/18/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/28/2022 | RAPHAEL ROSAS |
| Corrections Issued | 1/29/2022 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 2/15/2022 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 3/26/2022 | RAPHAEL ROSAS |
| Plan Check Approved | 4/16/2022 | RAPHAEL ROSAS |
| Building Plans Picked Up | 4/18/2022 | APPLICANT |
| Issued | 4/25/2022 | APPLICANT |
| CofO in Progress | 12/28/2022 | HAMIK HARTOUNIAN |
| Permit Finaled | 1/10/2023 | DEROLD HAUFF |
| CofO Issued | 1/10/2023 | DEROLD HAUFF |
| Permit Finaled | 1/10/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 2/3/2022 | CHRISTOPHER ROCHA |
| Roof/Waste drainage to street | Cleared | 2/3/2022 | CHRISTOPHER ROCHA |
| Eng Process Fee Ord 176,300 | Cleared | 2/4/2022 | CHRISTOPHER ROCHA |
| Sewer availability | Cleared | 2/4/2022 | CHRISTOPHER ROCHA |
| Grading Pre-Inspection | Cleared | 4/16/2022 | RAPHAEL ROSAS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Tangonan,, Jimmy Galeon; Lic. No.: C50500 | 19957 RHONA PLACE SAUGUS, CA 91350 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/15/2022 | Approved | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 6/15/2022 | Approved | HAMIK HARTOUNIAN |
| Pre-Inspection | 6/15/2022 | Approved | HAMIK HARTOUNIAN |
| Green Building Rough | 7/29/2022 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Wood Frame | 7/29/2022 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/8/2022 | Approved | HAMIK HARTOUNIAN |
| Green Building Rough | 8/8/2022 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Wood Frame | 8/8/2022 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 8/15/2022 | Approved | HAMIK HARTOUNIAN |
| Insulation | 8/18/2022 | Approved | RYAN SALAZAR |
| Drywall Nailing | 8/24/2022 | Approved | HAMIK HARTOUNIAN |
| Green Building Rough | 8/24/2022 | Approved | HAMIK HARTOUNIAN |
| Pre-Inspection | 8/24/2022 | Approved | HAMIK HARTOUNIAN |
| Wood Frame | 8/24/2022 | Approved | HAMIK HARTOUNIAN |
| Final | 11/28/2022 | Corrections Issued | HAMIK HARTOUNIAN |
| Green Building Final | 11/28/2022 | Approved | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 11/28/2022 | SGSOV Not Ready | HAMIK HARTOUNIAN |
| Smoke Detectors | 11/28/2022 | Approved | HAMIK HARTOUNIAN |
| Final | 12/8/2022 | Partial Inspection | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 12/8/2022 | SGSOV Approved | HAMIK HARTOUNIAN |
| Final | 12/28/2022 | OK to Issue CofO | HAMIK HARTOUNIAN |