4454 E ALUMNI AVE 90041

Certificate Information: 4454 E ALUMNI AVE 90041

Application / Permit
22014-20000-00191
Plan Check / Job No.
B22VN00715
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 15'-6" X 16'-6" DETACHED GARAGE AND ADD 13'-8.5" X 17'2.5" INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER ENGINEERING.
Permit Issued
Issued on 4/25/2022
Issuing Office
Current Status
CofO Issued on 1/10/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/18/2022 APPLICANT
Assigned to Plan Check Engineer 1/28/2022 RAPHAEL ROSAS
Corrections Issued 1/29/2022 RAPHAEL ROSAS
Applicant returned to address corrections 2/15/2022 RAPHAEL ROSAS
Applicant returned to address corrections 3/26/2022 RAPHAEL ROSAS
Plan Check Approved 4/16/2022 RAPHAEL ROSAS
Building Plans Picked Up 4/18/2022 APPLICANT
Issued 4/25/2022 APPLICANT
CofO in Progress 12/28/2022 HAMIK HARTOUNIAN
Permit Finaled 1/10/2023 DEROLD HAUFF
CofO Issued 1/10/2023 DEROLD HAUFF
Permit Finaled 1/10/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 2/3/2022 CHRISTOPHER ROCHA
Roof/Waste drainage to street Cleared 2/3/2022 CHRISTOPHER ROCHA
Eng Process Fee Ord 176,300 Cleared 2/4/2022 CHRISTOPHER ROCHA
Sewer availability Cleared 2/4/2022 CHRISTOPHER ROCHA
Grading Pre-Inspection Cleared 4/16/2022 RAPHAEL ROSAS

Contact Information

Contractor Owner-Builder       ,
Engineer Tangonan,, Jimmy Galeon; Lic. No.: C50500 19957 RHONA PLACE      SAUGUS, CA 91350

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/15/2022 Approved HAMIK HARTOUNIAN
Footing/Foundation/Slab 6/15/2022 Approved HAMIK HARTOUNIAN
Pre-Inspection 6/15/2022 Approved HAMIK HARTOUNIAN
Green Building Rough 7/29/2022 Not Ready for Inspection HAMIK HARTOUNIAN
Wood Frame 7/29/2022 Not Ready for Inspection HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 8/8/2022 Approved HAMIK HARTOUNIAN
Green Building Rough 8/8/2022 Not Ready for Inspection HAMIK HARTOUNIAN
Wood Frame 8/8/2022 Not Ready for Inspection HAMIK HARTOUNIAN
Interior/Exterior Lathing 8/15/2022 Approved HAMIK HARTOUNIAN
Insulation 8/18/2022 Approved RYAN SALAZAR
Drywall Nailing 8/24/2022 Approved HAMIK HARTOUNIAN
Green Building Rough 8/24/2022 Approved HAMIK HARTOUNIAN
Pre-Inspection 8/24/2022 Approved HAMIK HARTOUNIAN
Wood Frame 8/24/2022 Approved HAMIK HARTOUNIAN
Final 11/28/2022 Corrections Issued HAMIK HARTOUNIAN
Green Building Final 11/28/2022 Approved HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 11/28/2022 SGSOV Not Ready HAMIK HARTOUNIAN
Smoke Detectors 11/28/2022 Approved HAMIK HARTOUNIAN
Final 12/8/2022 Partial Inspection HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 12/8/2022 SGSOV Approved HAMIK HARTOUNIAN
Final 12/28/2022 OK to Issue CofO HAMIK HARTOUNIAN