17431 W BLYTHE ST 91325
Certificate Information: 17431 W BLYTHE ST 91325
- Application / Permit
- 22014-20000-00183
- Plan Check / Job No.
- B22VN00654
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED 18'-6" X 23'-6" ADDITION AND REMODEL TO (E) SFD. ALL WORK EPR ENGINEERING.
- Permit Issued
- Issued on 5/18/2022
- Issuing Office
- Current Status
- CofO Issued on 10/10/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/18/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/28/2022 | RAPHAEL ROSAS |
| Corrections Issued | 1/28/2022 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 3/13/2022 | RAPHAEL ROSAS |
| Plan Check Approved | 3/28/2022 | RAPHAEL ROSAS |
| Building Plans Picked Up | 3/30/2022 | APPLICANT |
| Issued | 5/18/2022 | APPLICANT |
| CofO in Progress | 9/15/2023 | RAUL OLAGI |
| CofO Issued | 10/10/2023 | RUBEN SALAS |
| Permit Finaled | 10/10/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 3/24/2022 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 3/24/2022 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 3/29/2022 | JOSE DUARTE-DIAZ |
Contact Information
| Contractor | Sonora Construction Inc; Lic. No.: 965168-B | 14411 KINGBURY ST MISSION HILLS, CA 913452338 |
| Engineer | Chiu,, Ivan Wai-Kuen; Lic. No.: C44672 | 2160 PARNELL WY ALTADENA, CA 91001 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/9/2022 | Not Ready for Inspection | ALAN MORELOS |
| Special/Order Compliance | 6/9/2022 | Partial Inspection | DEANDRE HOFFMAN |
| Underground Mechanical | 6/9/2022 | Corrections Issued | ALAN MORELOS |
| Footing/Foundation/Slab | 6/15/2022 | Approved | ALAN MORELOS |
| Underground Mechanical | 6/15/2022 | Approved | ALAN MORELOS |
| BUILDING-Rough-Frame | 9/19/2022 | Corrections Issued | RAUL OLAGI |
| ELECTRICAL-Rough | 9/19/2022 | Corrections Issued | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 9/19/2022 | Approved | RAUL OLAGI |
| HVAC-Rough | 9/19/2022 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Rough | 9/19/2022 | Corrections Issued | RAUL OLAGI |
| BUILDING-Rough-Frame | 11/7/2022 | Approved | RAUL OLAGI |
| ELECTRICAL-Rough | 11/7/2022 | Approved | RAUL OLAGI |
| Green Building Rough | 11/7/2022 | Approved | RAUL OLAGI |
| HVAC-Rough | 11/7/2022 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 11/7/2022 | Partial Approval | RAUL OLAGI |
| PLUMBING-Rough | 11/7/2022 | Approved | RAUL OLAGI |
| Shower Pan | 11/7/2022 | Approved | RAUL OLAGI |
| Insulation | 11/18/2022 | Approved | RAUL OLAGI |
| Drywall Nailing | 12/1/2022 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 12/1/2022 | Approved | RAUL OLAGI |
| ELECTRICAL-Final | 2/17/2023 | Corrections Issued | RAUL OLAGI |
| Final | 2/17/2023 | Corrections Issued | RAUL OLAGI |
| Green Building Final | 2/17/2023 | Approved | RAUL OLAGI |
| HVAC-Final | 2/17/2023 | Approved | RAUL OLAGI |
| PLUMBING-Final | 2/17/2023 | Approved | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 2/17/2023 | SGSOV Approved | RAUL OLAGI |
| Smoke Detectors | 2/17/2023 | Approved | RAUL OLAGI |
| Final | 2/22/2023 | Not Ready for Inspection | DAVID ANDERSON |
| Final | 9/15/2023 | OK to Issue CofO | RAUL OLAGI |