5435 N MORELLA AVE 91607
Certificate Information: 5435 N MORELLA AVE 91607
- Application / Permit
- 22014-20000-00180
- Plan Check / Job No.
- B22VN00639
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERSION OF THE (E) GARAGE TO AN ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c) AND (d), AND ADDITION OF 388 SF.
- Permit Issued
- Issued on 9/21/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 7/24/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/17/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/28/2022 | LUIS RINCON |
| Corrections Issued | 2/14/2022 | LUIS RINCON |
| Applicant returned to address corrections | 4/15/2022 | LUIS RINCON |
| Applicant returned to address corrections | 5/13/2022 | LUIS RINCON |
| Applicant returned to address corrections | 7/8/2022 | LUIS RINCON |
| Plan Check Approved | 8/10/2022 | LUIS RINCON |
| Building Plans Picked Up | 9/13/2022 | APPLICANT |
| Issued | 9/21/2022 | APPLICANT |
| CofO in Progress | 7/10/2024 | CHRISTOPHER ROJAS |
| Permit Finaled | 7/24/2024 | RUBEN SALAS |
| CofO Issued | 7/24/2024 | RUBEN SALAS |
| Permit Finaled | 7/24/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Hold | Cleared | 2/1/2022 | JASON SHEETS |
| Address approval | Cleared | 3/15/2022 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 3/15/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 3/16/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 3/16/2022 | CARLOS AGUILERA |
| Specific Plan | Cleared | 5/26/2022 | CORREY KITCHENS |
| ZI | Cleared | 5/26/2022 | CORREY KITCHENS |
Contact Information
| Architect | Justus,, John Karl; Lic. No.: C13537 | 245 RIVERVIEW DR AUBURN, CA 95603 |
| Contractor | Diallo Construction; Lic. No.: 965438-B | 535 S ALEXANDRIA AVENUE #308 LOS ANGELES, CA 90020 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/18/2022 | Partial Approval | JACK KARGODORIAN |
| Deputy Drilled-In Anchors | 2/1/2023 | Conditional Approval | MICHAEL SMITH |
| Footing/Foundation/Slab | 2/6/2023 | Corrections Issued | JACK KARGODORIAN |
| Footing/Foundation/Slab | 2/9/2023 | Approved | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/8/2023 | Partial Approval | JACK KARGODORIAN |
| Green Building Rough | 3/8/2023 | Approved | JACK KARGODORIAN |
| MERV13>=Rough | 3/8/2023 | Approved | JACK KARGODORIAN |
| ELECTRICAL-Rough | 3/20/2023 | Approved | JACK KARGODORIAN |
| PLUMBING-Rough | 3/20/2023 | Corrections Issued | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 3/30/2023 | Approved | JACK KARGODORIAN |
| Insulation | 4/3/2023 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 4/3/2023 | Partial Approval | JACK KARGODORIAN |
| Shower Pan | 4/3/2023 | Approved | JACK KARGODORIAN |
| Drywall Nailing | 4/10/2023 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 4/10/2023 | Partial Approval | JACK KARGODORIAN |
| Final | 7/24/2023 | Corrections Issued | JACK KARGODORIAN |
| Green Building Final | 7/24/2023 | Approved | JACK KARGODORIAN |
| MERV13>=Final | 7/24/2023 | Approved | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 7/24/2023 | SGSOV Approved | JACK KARGODORIAN |
| Smoke Detectors | 7/24/2023 | Approved | JACK KARGODORIAN |
| Final | 3/14/2024 | Corrections Issued | THOMAS FINNILA |
| Final | 6/25/2024 | OK to Issue CofO | CHRISTOPHER ROJAS |