1450 N SUNSET PLAZA DR 90069

Certificate Information: 1450 N SUNSET PLAZA DR 90069

Application / Permit
22014-20000-00175
Plan Check / Job No.
B22VN00625
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
INTERIOR REMODEL, ENCLOSURE PORTION OF EXISTING DECK, AND EXTEND DECK AT 2 LEVELS (ACROSS WIDTH OF BUILDING)TO (E) SINGLE FAMILY DWELLING. WORK PER ENGINEER.
Permit Issued
Issued on 9/26/2022
Issuing Office
Valley
Current Status
CofO Issued on 12/27/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/14/2022 APPLICANT
Assigned to Plan Check Engineer 2/4/2022 TROY DEGUZMAN
Corrections Issued 2/8/2022 TROY DEGUZMAN
Quality Review Completed 2/11/2022 OMID HEDAYAT
Building Plans Picked Up 2/14/2022 APPLICANT
Applicant returned to address corrections 6/9/2022 TROY DEGUZMAN
Applicant returned to address corrections 9/17/2022 DAWN MC NULTY
Plan Check Approved 9/19/2022 DAWN MC NULTY
Issued 9/26/2022 APPLICANT
CofO in Progress 11/21/2023 STUART CHAPMAN
CofO Issued 12/27/2023 DEROLD HAUFF
Permit Finaled 12/27/2023 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 2/26/2022 JEANETTE VONG
Sewer availability Cleared 2/26/2022 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 3/1/2022 JEANETTE VONG
Green Code Cleared 6/9/2022 TROY DEGUZMAN
Hydrant and Access approval Cleared 7/15/2022 KURT CORRAL
GPI Written Notices Cleared 8/8/2022 TROY DEGUZMAN
Grading Pre-Inspection Cleared 8/8/2022 TROY DEGUZMAN
Miscellaneous Cleared 8/11/2022 ALBERT TAM

Contact Information

Contractor Resto Group The; Lic. No.: 898290-B 311 N ROBERTSON SUITE 732      BEVERLY HILLS, CA 90211
Engineer Adams,, Robert Charles; Lic. No.: C21234 22129 BRYANT STREET      CANOGA PARK, CA 91304

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Floor/Roof Diaphrgm/Shear Wall 10/4/2022 Partial Approval RAUL BARAJAS
Structural Steel Frame 10/4/2022 Not Ready for Inspection RAUL BARAJAS
ELECTRICAL-Rough 12/8/2022 Not Ready for Inspection RAUL BARAJAS
PLUMBING-Rough 12/8/2022 Not Ready for Inspection RAUL BARAJAS
ELECTRICAL-Rough 12/14/2022 Approved STUART CHAPMAN
HVAC-Rough 12/14/2022 Approved STUART CHAPMAN
PLUMBING-Rough 12/14/2022 Approved STUART CHAPMAN
BUILDING-Rough-Frame 1/18/2023 Corrections Issued JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 1/20/2023 Partial Approval RAUL BARAJAS
Wood Frame 1/20/2023 Not Ready for Inspection RAUL BARAJAS
BUILDING-Rough-Frame 3/17/2023 Approved STUART CHAPMAN
Insulation 3/17/2023 Approved STUART CHAPMAN
Shower Pan 3/17/2023 Approved STUART CHAPMAN
Drywall Nailing 4/6/2023 Approved RAUL BARAJAS
Interior/Exterior Lathing 5/1/2023 Approved RAUL BARAJAS
Interior/Exterior Lathing 5/4/2023 Approved RAUL BARAJAS
Service/Power Release 7/31/2023 Partial Inspection STUART CHAPMAN
ELECTRICAL-Final 8/9/2023 Approved RAUL BARAJAS
Final 8/15/2023 Corrections Issued RAUL BARAJAS
HVAC-Final 8/15/2023 Not Ready for Inspection RAUL BARAJAS
PLUMBING-Final 8/15/2023 Not Ready for Inspection RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 8/15/2023 SGSOV Not Ready RAUL BARAJAS
Smoke Detectors 8/15/2023 Approved RAUL BARAJAS
HVAC-Final 9/6/2023 Not Ready for Inspection STUART CHAPMAN
PLUMBING-Final 9/6/2023 Not Ready for Inspection STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 9/6/2023 SGSOV Not Ready STUART CHAPMAN
HVAC-Final 9/7/2023 Partial Inspection RAUL BARAJAS
PLUMBING-Final 9/7/2023 Partial Inspection RAUL BARAJAS
Final 10/4/2023 Not Ready for Inspection STUART CHAPMAN
HVAC-Final 10/4/2023 Not Ready for Inspection STUART CHAPMAN
PLUMBING-Final 10/4/2023 Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 10/4/2023 SGSOV Not Ready STUART CHAPMAN
Final 11/21/2023 OK to Issue CofO STUART CHAPMAN
HVAC-Final 11/21/2023 Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 11/21/2023 SGSOV Approved STUART CHAPMAN