20737-20741 W MARTHA ST 91367
Certificate Information: 20737-20741 W MARTHA ST 91367
- Application / Permit
- 22014-20000-00130
- Plan Check / Job No.
- B22VN00402
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) GARAGE TO JADU AND AN ADDITION OF A 2ND FLOOR TO CREATE A NEW ACCESSORY DWELLING UNIT TO THE (E) S.F.D . ADDITION TO THE S.F.D ON THE FIRST FLOOR FIRE SPRINKLERS WILL BE REQUIRED (SEE COMMENTS)
- Permit Issued
- Issued on 7/27/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 10/23/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/12/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/17/2022 | MINA HABIB |
| Corrections Issued | 2/28/2022 | MINA HABIB |
| Quality Review Completed | 3/3/2022 | FARUK SEZER |
| Building Plans Picked Up | 3/21/2022 | APPLICANT |
| Applicant returned to address corrections | 2/10/2023 | MINA HABIB |
| Applicant returned to address corrections | 4/20/2023 | MINA HABIB |
| Applicant returned to address corrections | 5/18/2023 | MINA HABIB |
| Plan Check Approved | 5/30/2023 | MINA HABIB |
| Issued | 7/27/2023 | APPLICANT |
| CofO in Progress | 9/15/2025 | ALEXANDER HANDY |
| CofO in Progress | 10/2/2025 | ROBERT GOLD |
| CofO in Progress | 10/2/2025 | ROBERT GOLD |
| Permit Finaled | 10/23/2025 | JOHN JANSON |
| CofO Issued | 10/23/2025 | JOHN JANSON |
| Permit Finaled | 10/23/2025 | JOHN JANSON |
Permit Application Clearance Information
| DAS Clearance | Cleared | 3/3/2022 | MINA HABIB |
| Address approval | Cleared | 4/22/2022 | ROMAN GUTIERREZ |
| Eng Process Fee Ord 176,300 | Cleared | 4/25/2022 | ROMAN GUTIERREZ |
| Sewer availability | Cleared | 4/25/2022 | ROMAN GUTIERREZ |
| Hydrant and Access approval | Cleared | 10/13/2022 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 12/27/2022 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 1/10/2023 | COLIN LOREDO |
| Miscellaneous | Cleared | 1/13/2023 | DANG NGUYEN |
| Grading Pre-Inspection | Cleared | 1/19/2023 | KIRK LINKLATER |
| GPI Written Notices | Cleared | 5/18/2023 | MINA HABIB |
| Green Code | Cleared | 5/18/2023 | MINA HABIB |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Babapirzadeh,, Ghazal; Lic. No.: C90480 | 7270 HILLSIDE AVE APT 306 LOS ANGELES, CA 90046 |
Inspector Information
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/3/2023 | Approved | ALEXANDER HANDY |
| Excavation/Setback/Form/Re-Bar | 8/28/2023 | Not Ready for Inspection | ALEXANDER HANDY |
| Excavation/Setback/Form/Re-Bar | 9/1/2023 | Corrections Issued | HORACE FULTZ |
| Deputy Drilled-In Anchors | 9/8/2023 | Conditional Approval | ALEXANDER HANDY |
| Excavation/Setback/Form/Re-Bar | 9/11/2023 | Conditional Approval | ALEXANDER HANDY |
| Excavation/Setback/Form/Re-Bar | 9/22/2023 | No Access for Inspection | ALEXANDER HANDY |
| Excavation/Setback/Form/Re-Bar | 10/2/2023 | Approved | HORACE FULTZ |
| Wood Frame | 10/25/2023 | Partial Approval | ALEXANDER HANDY |
| Floor/Roof Diaphrgm/Shear Wall | 11/8/2023 | Partial Approval | ALEXANDER HANDY |
| Floor/Roof Diaphrgm/Shear Wall | 11/13/2023 | Partial Approval | ALEXANDER HANDY |
| ELECTRICAL-Rough | 2/2/2024 | Corrections Issued | JEFFREY PARD |
| PLUMBING-Rough | 2/2/2024 | Corrections Issued | JEFFREY PARD |
| ELECTRICAL-Rough | 2/9/2024 | Not Ready for Inspection | ALEXANDER HANDY |
| PLUMBING-Rough | 2/9/2024 | Partial Inspection | ARUTYUN MADATYAN |
| Special/Order Compliance | 2/9/2024 | Partial Inspection | ARUTYUN MADATYAN |
| ELECTRICAL-Rough | 2/15/2024 | Approved | ALEXANDER HANDY |
| Interior/Exterior Lathing | 2/15/2024 | Partial Approval | ALEXANDER HANDY |
| PLUMBING-Rough | 2/15/2024 | Approved | ALEXANDER HANDY |
| Gas Test | 4/15/2024 | Partial Approval | ALEXANDER HANDY |
| Insulation | 4/15/2024 | Corrections Issued | ALEXANDER HANDY |
| Insulation | 4/22/2024 | Approved | ALEXANDER HANDY |
| Deputy Wood Construction | 5/10/2024 | Conditional Approval | ARUTYUN MADATYAN |
| Wood Frame | 5/16/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Wood Frame | 5/21/2024 | Approved | ALEXANDER HANDY |
| Drywall Nailing | 6/27/2024 | Approved | ALEXANDER HANDY |
| Green Building Rough | 6/27/2024 | Approved | ALEXANDER HANDY |
| Shower Pan | 6/27/2024 | Approved | ALEXANDER HANDY |
| ELECTRICAL-Rough | 7/8/2024 | Approved | ARUTYUN MADATYAN |
| Interior/Exterior Lathing | 7/8/2024 | Partial Approval | ARUTYUN MADATYAN |
| Shower Pan | 7/8/2024 | Approved | ARUTYUN MADATYAN |
| ELECTRICAL-Final | 10/24/2024 | Corrections Issued | ALEXANDER HANDY |
| Special/Order Compliance | 11/20/2024 | Not Ready for Inspection | ALEXANDER HANDY |
| ELECTRICAL-Final | 1/24/2025 | Not Ready for Inspection | DAVID SCANTLIN |
| Special/Order Compliance | 3/3/2025 | Partial Inspection | ALEXANDER HANDY |
| Special/Order Compliance | 3/3/2025 | Partial Inspection | HENRY KIM |
| BUILDING-Rough-Frame | 4/29/2025 | Approved | ALEXANDER HANDY |
| Final | 4/29/2025 | Corrections Issued | ALEXANDER HANDY |
| Footing/Foundation/Slab | 4/29/2025 | Approved | ALEXANDER HANDY |
| Green Building Final | 4/29/2025 | Not Ready for Inspection | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 4/29/2025 | SGSOV Not Ready | ALEXANDER HANDY |
| Smoke Detectors | 4/29/2025 | Not Ready for Inspection | ALEXANDER HANDY |
| Special/Order Compliance | 4/29/2025 | Approved | ROBERT GOLD |
| ELECTRICAL-Final | 5/6/2025 | Partial Inspection | ALEXANDER HANDY |
| Special/Order Compliance | 5/6/2025 | Approved | ROBERT GOLD |
| ELECTRICAL-Final | 5/13/2025 | Partial Inspection | ALEXANDER HANDY |
| ELECTRICAL-Final | 6/24/2025 | Not Ready for Inspection | ROBERT GOLD |
| ELECTRICAL-Final | 8/12/2025 | Not Ready for Inspection | GEVORK IPCHYAN |
| ELECTRICAL-Final | 8/13/2025 | Corrections Issued | ALEXANDER HANDY |
| Final | 8/25/2025 | Corrections Issued | ALEXANDER HANDY |
| Special/Order Compliance | 8/25/2025 | Partial Inspection | ROBERT GOLD |
| Final | 9/8/2025 | Corrections Issued | ALEXANDER HANDY |
| Green Building Final | 9/8/2025 | Approved | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 9/8/2025 | SGSOV Not Ready | ALEXANDER HANDY |
| Smoke Detectors | 9/8/2025 | Approved | ALEXANDER HANDY |
| Special/Order Compliance | 9/8/2025 | Approved | ROBERT GOLD |
| ELECTRICAL-Final | 9/12/2025 | Approved | ALEXANDER HANDY |
| Final | 9/12/2025 | Partial Approval | ALEXANDER HANDY |
| HVAC-Final | 9/12/2025 | Approved | ALEXANDER HANDY |
| PLUMBING-Final | 9/12/2025 | Approved | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 9/12/2025 | SGSOV Approved | ALEXANDER HANDY |
| Service/Power Release | 9/12/2025 | Approved | ALEXANDER HANDY |
| Final | 10/2/2025 | Corrections Issued | ROBERT GOLD |