913 E MILWOOD AVE 90291

Certificate Information: 913 E MILWOOD AVE 90291

Application / Permit
22014-20000-00129
Plan Check / Job No.
B22VN00400
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Removal of 341 SF of first floor, ground floor addition of 198 SF, and interior remodel of 1-story portion to an existing 2-story single family with attached garage.
Permit Issued
Issued on 5/17/2024
Issuing Office
Current Status
CofO Issued on 8/5/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/25/2022 APPLICANT
Assigned to Plan Check Engineer 2/24/2022 CHUNG-WEN CHUANG
Corrections Issued 3/16/2022 CHUNG-WEN CHUANG
Quality Review Completed 3/25/2022 TEODORO DIAZ RODRIGUEZ
Building Plans Picked Up 4/13/2022 APPLICANT
Applicant returned to address corrections 1/30/2024 VICTOR CHEN
Plan Check Approved 2/20/2024 VICTOR CHEN
Issued 5/17/2024 APPLICANT
CofO in Progress 7/29/2025 JESUS RODRIGUEZ
Permit Finaled 8/5/2025 RICHARD STEINBACH
CofO Issued 8/5/2025 RICHARD STEINBACH
Permit Finaled 8/5/2025 RICHARD STEINBACH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/12/2023 ANTHONY MAINEZ
Roof/Waste drainage to street Cleared 1/12/2023 ANTHONY MAINEZ
Coastal Zone Cleared 2/8/2023 RUBEN VASQUEZ
Specific Plan Cleared 8/16/2023 SIENNA KUO
Specific Plan Cleared 8/26/2023 EDUARDO HERMOSO

Contact Information

Contractor Makeover Builders Inc; Lic. No.: 986740-B 21781 VENTURA BLVD UNIT 634      WOODLAND HILLS, CA 91364
Engineer Babapirzadeh,, Ghazal; Lic. No.: C90480 7270 HILLSIDE AVE   APT 306    LOS ANGELES, CA 90046

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/1/2024 Partial Approval HERBERT GIRON
Footing/Foundation/Slab 10/10/2024 Approved HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 12/3/2024 Corrections Issued HERBERT GIRON
ELECTRICAL-Rough 12/10/2024 Corrections Issued HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 12/10/2024 Approved HERBERT GIRON
HVAC-Rough 12/10/2024 Corrections Issued HERBERT GIRON
PLUMBING-Rough 12/10/2024 Approved HERBERT GIRON
ELECTRICAL-Rough 12/19/2024 Approved MICHAEL ALLEN
HVAC-Rough 12/19/2024 Approved MICHAEL ALLEN
Interior/Exterior Lathing 12/19/2024 Partial Approval MICHAEL ALLEN
Insulation 12/31/2024 Approved MICHAEL ALLEN
BUILDING-Rough-Frame 1/13/2025 Approved HERBERT GIRON
Drywall Nailing 1/13/2025 Approved HERBERT GIRON
Green Building Rough 1/13/2025 Approved HERBERT GIRON
Interior/Exterior Lathing 1/13/2025 Approved HERBERT GIRON
Shower Pan 1/13/2025 Approved HERBERT GIRON
ELECTRICAL-Final 7/2/2025 Approved JESUS RODRIGUEZ
Final 7/2/2025 Corrections Issued JESUS RODRIGUEZ
Green Building Final 7/2/2025 Approved JESUS RODRIGUEZ
HVAC-Final 7/2/2025 Approved JESUS RODRIGUEZ
PLUMBING-Final 7/2/2025 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 7/2/2025 SGSOV Not Ready JESUS RODRIGUEZ
Smoke Detectors 7/2/2025 Approved JESUS RODRIGUEZ
Final 7/11/2025 Not Ready for Inspection JESUS PINEDA
SGSOV-Seismic Gas S/O Valve 7/11/2025 SGSOV Approved JESUS PINEDA
Final 7/23/2025 No Access for Inspection TEMISTOCLES CAAL
Final 7/28/2025 OK to Issue CofO JESUS RODRIGUEZ