20232 W HARTLAND ST 91306
Certificate Information: 20232 W HARTLAND ST 91306
- Application / Permit
- 22014-20000-00114
- Plan Check / Job No.
- B22VN00358
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) IRREGULARLY SHAPED ADDITION (41'-6" X 15') TO (E) SFD FOR NEW BEDROOM, LIVING ROOM, SITTING ROOM, AND (2) BATHROOMS. CONVERT EX BEDRM INTO DEN. WORK PER ENGINEER.
- Permit Issued
- Issued on 12/29/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 8/7/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/17/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/19/2022 | ROSENDO MEDINA |
| Corrections Issued | 1/20/2022 | ROSENDO MEDINA |
| Applicant returned to address corrections | 10/21/2022 | DANIEL ABRAMYAN |
| Applicant returned to address corrections | 11/28/2022 | MADISON ODELL |
| Applicant returned to address corrections | 12/9/2022 | HAYATO TSUCHIYA |
| Plan Check Approved | 12/16/2022 | ISIS ARGUETA |
| Issued | 12/29/2022 | APPLICANT |
| CofO in Progress | 8/1/2024 | ALEXANDER HANDY |
| Permit Finaled | 8/7/2024 | JOHN JANSON |
| CofO Issued | 8/7/2024 | JOHN JANSON |
| Permit Finaled | 8/7/2024 | JOHN JANSON |
Permit Application Clearance Information
| Low Impact Development | Cleared | 10/5/2022 | LUIS LUVANO |
| Eng Process Fee Ord 176,300 | Cleared | 10/12/2022 | COLIN LOREDO |
| Sewer availability | Cleared | 10/12/2022 | COLIN LOREDO |
| Roof/Waste drainage to street | Cleared | 10/13/2022 | COLIN LOREDO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Vasquez,, Mario A; Lic. No.: C89006 | 1942 SPANISH BROOM DR PALMDALE, CA 93550 |
Inspector Information
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 9/26/2023 | Partial Approval | ALEXANDER HANDY |
| Excavation/Setback/Form/Re-Bar | 10/3/2023 | Approved | JOHN KIDWELL |
| BUILDING-Rough-Frame | 11/13/2023 | Not Ready for Inspection | HORACE FULTZ |
| Floor/Roof Diaphrgm/Shear Wall | 11/13/2023 | Partial Approval | HORACE FULTZ |
| Green Building Rough | 11/13/2023 | Not Ready for Inspection | HORACE FULTZ |
| BUILDING-Rough-Frame | 12/4/2023 | Approved | ALEXANDER HANDY |
| ELECTRICAL-Rough | 12/4/2023 | Approved | ALEXANDER HANDY |
| Floor/Roof Diaphrgm/Shear Wall | 12/4/2023 | Approved | ALEXANDER HANDY |
| Green Building Rough | 12/4/2023 | Approved | ALEXANDER HANDY |
| Interior/Exterior Lathing | 12/4/2023 | Partial Approval | ALEXANDER HANDY |
| PLUMBING-Rough | 12/4/2023 | Corrections Issued | ALEXANDER HANDY |
| Insulation | 12/15/2023 | Approved | ALEXANDER HANDY |
| Drywall Nailing | 12/22/2023 | Approved | MORRIS JACKSON |
| Interior/Exterior Lathing | 12/22/2023 | Approved | MORRIS JACKSON |
| Final | 5/23/2024 | Corrections Issued | ALEXANDER HANDY |
| Footing/Foundation/Slab | 5/23/2024 | Approved | ALEXANDER HANDY |
| Gas Test | 5/23/2024 | Approved | ALEXANDER HANDY |
| Green Building Final | 5/23/2024 | Not Ready for Inspection | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 5/23/2024 | SGSOV Approved | ALEXANDER HANDY |
| Smoke Detectors | 5/23/2024 | Approved | ALEXANDER HANDY |
| ELECTRICAL-Final | 8/1/2024 | Approved | ALEXANDER HANDY |
| Final | 8/1/2024 | OK to Issue CofO | ALEXANDER HANDY |
| Green Building Final | 8/1/2024 | Approved | ALEXANDER HANDY |
| HVAC-Final | 8/1/2024 | Approved | ALEXANDER HANDY |
| PLUMBING-Final | 8/1/2024 | Approved | ALEXANDER HANDY |