16430-16432 W MCKEEVER ST 91344

Certificate Information: 16430-16432 W MCKEEVER ST 91344

Application / Permit
22014-20000-00089
Plan Check / Job No.
B22VN00262
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD 18' X 20' TO AND CONVERT (E) 19'6" X 20' ATTACHED GARAGE TO (E) SFD TO ACCESSORY DWELLING UNIT AS PER LAMC 12.22.A.33 (C) AND (E), ALL WORK PER ENGINEERING
Permit Issued
Issued on 4/28/2022
Issuing Office
Current Status
CofO Issued on 4/18/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/10/2022 APPLICANT
Assigned to Plan Check Engineer 2/10/2022 RARES BODEA
Corrections Issued 2/18/2022 RARES BODEA
Quality Review Completed 2/24/2022 STEVEN KIM
Building Plans Picked Up 2/25/2022 APPLICANT
Plan Check Approved 4/13/2022 RARES BODEA
Issued 4/28/2022 APPLICANT
CofO in Progress 3/28/2023 JAVIER RAMOS JR
Permit Finaled 4/18/2023 MICHAEL SMITH
CofO Issued 4/18/2023 MICHAEL SMITH
Permit Finaled 4/18/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 2/28/2022 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 2/28/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 3/1/2022 CARLOS AGUILERA
Sewer availability Cleared 3/1/2022 CARLOS AGUILERA
Construction near power lines Cleared 3/29/2022 RIDWAN HARDY
Construction within easement Cleared 3/29/2022 RIDWAN HARDY
Grading Pre-Inspection Cleared 4/12/2022 KIRK LINKLATER

Contact Information

Contractor Owner-Builder       ,
Engineer Chatsky,, German; Lic. No.: C84153 3876 HUNTERS GROVE CT      MOORPARK, CA 93021

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/23/2022 Partial Approval RAUL OLAGI
Footing/Foundation/Slab 5/27/2022 Partial Approval JAVIER RAMOS JR
PLUMBING-Rough 5/27/2022 Partial Approval JAVIER RAMOS JR
Footing/Foundation/Slab 6/7/2022 Approved JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 6/29/2022 Partial Approval JAVIER RAMOS JR
Wood Frame 7/13/2022 Corrections Issued DEANDRE HOFFMAN
Deputy Wood Construction 7/18/2022 Conditional Approval JAVIER RAMOS JR
Rough-Elec/Plmb/HVAC 7/28/2022 Approved JAVIER RAMOS JR
Underground Mechanical 7/28/2022 Partial Approval JAVIER RAMOS JR
Green Building Rough 8/9/2022 Approved JAVIER RAMOS JR
Insulation 8/9/2022 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 8/9/2022 Approved JAVIER RAMOS JR
Drywall Nailing 8/16/2022 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 10/3/2022 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 12/20/2022 Partial Approval JAVIER RAMOS JR
Final 12/20/2022 Corrections Issued JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 12/20/2022 SGSOV Approved JAVIER RAMOS JR
Smoke Detectors 12/20/2022 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 1/3/2023 Approved JAVIER RAMOS JR
Final 1/3/2023 Corrections Issued JAVIER RAMOS JR
Green Building Final 1/3/2023 Not Ready for Inspection JAVIER RAMOS JR
MERV13>=Final 1/3/2023 Approved JAVIER RAMOS JR
MERV13>=Rough 1/3/2023 Approved JAVIER RAMOS JR
Final 3/24/2023 OK to Issue CofO JAVIER RAMOS JR
Green Building Final 3/24/2023 Approved JAVIER RAMOS JR