3649 1/2 S 7TH AVE 90018
Certificate Information: 3649 1/2 S 7TH AVE 90018
- Application / Permit
- 22014-20000-00078
- Plan Check / Job No.
- B22VN00221
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 18'-0" X 10'-0" ADDITION TO AND CONVERT EX. DETACHED GARAGE INTO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). WORK DONE PER WFPP.
- Permit Issued
- Issued on 8/16/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 8/23/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/7/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/20/2022 | ARTIN ZARUKIAN |
| Corrections Issued | 1/22/2022 | ARTIN ZARUKIAN |
| Plan Check Approved | 8/16/2022 | ROSENDO MEDINA |
| Issued | 8/16/2022 | APPLICANT |
| CofO in Progress | 8/2/2023 | CALEB MEISTER |
| Permit Finaled | 8/23/2023 | DEROLD HAUFF |
| CofO Issued | 8/23/2023 | DEROLD HAUFF |
| Permit Finaled | 8/23/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 2/1/2022 | TREVOR QUAN |
| Roof/Waste drainage to street | Cleared | 2/1/2022 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 2/2/2022 | TREVOR QUAN |
| Sewer availability | Cleared | 2/2/2022 | TREVOR QUAN |
| HPOZ | Cleared | 7/28/2022 | DANIEL MATA |
| ZI | Cleared | 7/28/2022 | DANIEL MATA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 12/2/2022 | Conditional Approval | BRENDAN MORELLI |
| Footing/Foundation/Slab | 12/9/2022 | Approved | MICHAEL LEWIS |
| Underground Mechanical | 12/9/2022 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 1/27/2023 | Corrections Issued | CALEB MEISTER |
| Green Building Rough | 1/27/2023 | Not Ready for Inspection | CALEB MEISTER |
| Rough-Elec/Plmb/HVAC | 1/27/2023 | Corrections Issued | CALEB MEISTER |
| BUILDING-Rough-Frame | 2/21/2023 | Approved | CALEB MEISTER |
| Green Building Rough | 2/21/2023 | Approved | CALEB MEISTER |
| Insulation | 3/3/2023 | Approved | CALEB MEISTER |
| Drywall Nailing | 3/8/2023 | Approved | MICHAEL LEWIS |
| PLUMBING-Final | 7/5/2023 | Not Ready for Inspection | CALEB MEISTER |
| Final | 7/13/2023 | Not Ready for Inspection | CALEB MEISTER |
| Green Building Final | 7/13/2023 | Not Ready for Inspection | CALEB MEISTER |
| SGSOV-Seismic Gas S/O Valve | 7/13/2023 | SGSOV Not Ready | CALEB MEISTER |
| Smoke Detectors | 7/13/2023 | Approved | CALEB MEISTER |
| ELECTRICAL-Final | 8/1/2023 | Approved | CALEB MEISTER |
| ELECTRICAL-Rough | 8/1/2023 | Approved | CALEB MEISTER |
| Final | 8/1/2023 | OK to Issue CofO | CALEB MEISTER |
| Green Building Final | 8/1/2023 | Approved | CALEB MEISTER |
| HVAC-Final | 8/1/2023 | Approved | CALEB MEISTER |
| HVAC-Rough | 8/1/2023 | Approved | CALEB MEISTER |
| PLUMBING-Final | 8/1/2023 | Approved | CALEB MEISTER |
| PLUMBING-Rough | 8/1/2023 | Approved | CALEB MEISTER |
| SGSOV-Seismic Gas S/O Valve | 8/1/2023 | SGSOV Approved | CALEB MEISTER |