17734 W LUDLOW ST 91344

Certificate Information: 17734 W LUDLOW ST 91344

Application / Permit
22014-20000-00074
Plan Check / Job No.
B22VN00219
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 9' X 24'-10" AND 12' X 36'-1" ADDITION TO SFD FOR (N) LAUNDRY ROOM AND BATHROOM AND TRELLIS PATIO COVER AND INTERIOR REMODEL. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 2/28/2022
Issuing Office
Current Status
CofO Issued on 8/18/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/7/2022 APPLICANT
Assigned to Plan Check Engineer 1/20/2022 RAPHAEL ROSAS
Corrections Issued 1/20/2022 RAPHAEL ROSAS
Issued 2/28/2022 APPLICANT
Building Plans Picked Up 2/28/2022 APPLICANT
CofO in Progress 8/17/2023 STEVEN BACK
Permit Finaled 8/18/2023 DANIEL ORRANTE
CofO Issued 8/18/2023 DANIEL ORRANTE
Permit Finaled 8/18/2023 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/1/2022 DAGOVERTO GUERRERO
Roof/Waste drainage to street Cleared 2/1/2022 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,
Engineer Rhee,, Kyle; Lic. No.: C78215 2753 WAVERLY DR 403      LOS ANGELES, CA 90039

Inspector Information

JEFFREY PARD, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI
STEVEN BACK, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/13/2022 Partial Approval DAVID SCANTLIN
Footing/Foundation/Slab 4/26/2022 Approved DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 6/28/2022 Approved DAVID SCANTLIN
Gas Test 6/28/2022 Approved DAVID SCANTLIN
Green Building Rough 6/28/2022 Not Ready for Inspection DAVID SCANTLIN
Rough-Elec/Plmb/HVAC 6/28/2022 Approved DAVID SCANTLIN
Insulation 7/18/2022 Not Ready for Inspection DAVID SCANTLIN
Interior/Exterior Lathing 7/18/2022 Partial Approval DAVID SCANTLIN
Drywall Nailing 8/2/2022 Approved CHRIS CHRISTENSEN
Green Building Rough 8/2/2022 Approved CHRIS CHRISTENSEN
Insulation 8/2/2022 Approved CHRIS CHRISTENSEN
Shower Pan 8/17/2022 Approved KRISTEN CAUSEY
Interior/Exterior Lathing 8/23/2022 Approved DAVID SCANTLIN
BUILDING-Rough-Frame 4/18/2023 Not Ready for Inspection DAVID SCANTLIN
Final 4/18/2023 Not Ready for Inspection DAVID SCANTLIN
Green Building Final 4/18/2023 Not Ready for Inspection DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 4/18/2023 SGSOV Not Ready DAVID SCANTLIN
Smoke Detectors 4/18/2023 Not Ready for Inspection DAVID SCANTLIN
BUILDING-Rough-Frame 5/31/2023 Not Ready for Inspection STEVEN BACK
Final 5/31/2023 Corrections Issued STEVEN BACK
Green Building Final 5/31/2023 Approved STEVEN BACK
SGSOV-Seismic Gas S/O Valve 5/31/2023 SGSOV Not Ready STEVEN BACK
Smoke Detectors 5/31/2023 Approved STEVEN BACK
BUILDING-Rough-Frame 8/17/2023 Approved STEVEN BACK
Final 8/17/2023 OK to Issue CofO STEVEN BACK
SGSOV-Seismic Gas S/O Valve 8/17/2023 SGSOV Approved STEVEN BACK
Special/Order Compliance 8/17/2023 Partial Inspection JEFFREY HARTLINE