1645 N GARDNER ST 90046
Certificate Information: 1645 N GARDNER ST 90046
- Application / Permit
- 22014-20000-00070
- Plan Check / Job No.
- B22VN00212
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 7' X 16' ADDITION TO AND CONVERT THE (E) DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A33.
- Permit Issued
- Issued on 2/18/2022
- Issuing Office
- Current Status
- CofO Issued on 12/15/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/11/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/21/2022 | SERGIO MUNIZ |
| Corrections Issued | 1/22/2022 | SERGIO MUNIZ |
| Applicant returned to address corrections | 2/8/2022 | SERGIO MUNIZ |
| Plan Check Approved | 2/18/2022 | SERGIO MUNIZ |
| Issued | 2/18/2022 | APPLICANT |
| Building Plans Picked Up | 2/28/2022 | APPLICANT |
| CofO in Progress | 12/9/2022 | BRIAN SULLIVAN |
| Permit Finaled | 12/15/2022 | DEROLD HAUFF |
| CofO Issued | 12/15/2022 | DEROLD HAUFF |
| Permit Finaled | 12/15/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 1/27/2022 | CINDY QI |
| Roof/Waste drainage to street | Cleared | 1/27/2022 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 1/31/2022 | CINDY QI |
| Sewer availability | Cleared | 1/31/2022 | CINDY QI |
| HPOZ | Cleared | 2/1/2022 | AMANDA KAINER |
Contact Information
| Architect | Dembsky,, Amit; Lic. No.: C30383 | 5739 KANAN ROAD # 133 AGOURA HILLS, CA 91301 |
| Contractor | My Home Builders Inc; Lic. No.: 1002927-B | 20720 VENTURA BLVD #280 WOODLAND HILLS, CA 91364 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 5/17/2022 | Approved | RAUL BARAJAS |
| Underground Mechanical | 5/17/2022 | Approved | RAUL BARAJAS |
| Footing/Foundation/Slab | 5/19/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 5/26/2022 | Approved | RAUL BARAJAS |
| ELECTRICAL-Rough | 6/29/2022 | Approved | RAUL BARAJAS |
| HVAC-Rough | 6/29/2022 | Not Ready for Inspection | RAUL BARAJAS |
| PLUMBING-Rough | 6/29/2022 | Approved | RAUL BARAJAS |
| Sewer | 6/29/2022 | Approved | RAUL BARAJAS |
| Insulation | 7/5/2022 | Approved | RAUL BARAJAS |
| Interior/Exterior Lathing | 7/5/2022 | Approved | RAUL BARAJAS |
| Sewer | 7/5/2022 | Approved | RAUL BARAJAS |
| Shower Pan | 7/5/2022 | Approved | RAUL BARAJAS |
| Drywall Nailing | 7/15/2022 | Approved | RAUL BARAJAS |
| BUILDING-Rough-Frame | 11/4/2022 | Approved | BRIAN SULLIVAN |
| ELECTRICAL-Final | 11/4/2022 | Approved | BRIAN SULLIVAN |
| Final | 11/4/2022 | Conditional Approval | BRIAN SULLIVAN |
| Green Building Final | 11/4/2022 | Approved | BRIAN SULLIVAN |
| Green Building Rough | 11/4/2022 | Approved | BRIAN SULLIVAN |
| HVAC-Final | 11/4/2022 | Approved | BRIAN SULLIVAN |
| PLUMBING-Final | 11/4/2022 | Approved | BRIAN SULLIVAN |
| SGSOV-Seismic Gas S/O Valve | 11/4/2022 | SGSOV Approved | BRIAN SULLIVAN |
| Smoke Detectors | 11/4/2022 | Approved | BRIAN SULLIVAN |
| Final | 12/9/2022 | OK to Issue CofO | BRIAN SULLIVAN |