5772 W 74TH ST 90045

Certificate Information: 5772 W 74TH ST 90045

Application / Permit
22014-20000-00059
Plan Check / Job No.
B22VN00179
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD (31'-6"x26'-0") IRR SHAPE AT FRONT AND (16'-4"x 15'-0") IRR SHAPE CLOSETS & CONVERT (E) PLAY ROOM TO BEDROOM-3 @ REAR & INTERIOR REMODEL , RE-ROOF ENTIRE ROOF TO (E) ONE STORY SINGLE FAMILY DWELLING.
Permit Issued
Issued on 7/27/2022
Issuing Office
Current Status
CofO Issued on 11/8/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/10/2022 APPLICANT
Assigned to Plan Check Engineer 2/10/2022 TROY DEGUZMAN
Corrections Issued 2/18/2022 TROY DEGUZMAN
Quality Review Completed 2/18/2022 OMID HEDAYAT
Building Plans Picked Up 3/1/2022 APPLICANT
Applicant returned to address corrections 6/2/2022 TROY DEGUZMAN
Applicant returned to address corrections 7/8/2022 TROY DEGUZMAN
Plan Check Approved 7/27/2022 TROY DEGUZMAN
Issued 7/27/2022 APPLICANT
CofO in Progress 10/26/2023 JESUS RODRIGUEZ
Permit Finaled 11/8/2023 DANIEL ORRANTE
CofO Issued 11/8/2023 DANIEL ORRANTE
Permit Finaled 11/8/2023 DANIEL ORRANTE

Permit Application Clearance Information

Sewer availability Cleared 4/20/2022 JENSON LEE
Specific Plan Cleared 4/20/2022 ANNA VIDAL
Eng Process Fee Ord 176,300 Cleared 4/21/2022 JENSON LEE
Specific Plan Cleared 4/27/2022 FREDDY GARCIA
GPI Written Notices Cleared 5/31/2022 JONATHAN HOM
Grading Pre-Inspection Cleared 5/31/2022 JONATHAN HOM
Low Impact Development Cleared 7/1/2022 ROGELIO CORTES
Roof/Waste drainage to street Cleared 7/7/2022 JENSON LEE
Green Code Cleared 7/8/2022 TROY DEGUZMAN

Contact Information

Architect Noteware,, Brian Arthur; Lic. No.: C21514 845 20TH STREET, #106      SANTA MONICA, CA 90403
Contractor Owner-Builder       ,

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/15/2022 Approved BOBBY KEY
Footing/Foundation/Slab 8/15/2022 Approved BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 8/22/2022 Partial Approval BOBBY KEY
PLUMBING-Rough 8/22/2022 Partial Approval BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 10/6/2022 Partial Approval BOBBY KEY
Gas Test 10/21/2022 Partial Approval BOBBY KEY
HVAC-Rough 10/21/2022 Approved BOBBY KEY
Interior/Exterior Lathing 10/21/2022 Partial Approval BOBBY KEY
PLUMBING-Rough 10/21/2022 Approved BOBBY KEY
BUILDING-Rough-Frame 11/1/2022 Corrections Issued BOBBY KEY
ELECTRICAL-Rough 11/1/2022 Approved BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 11/1/2022 Approved BOBBY KEY
BUILDING-Rough-Frame 11/8/2022 Conditional Approval BOBBY KEY
Green Building Rough 11/8/2022 Approved BOBBY KEY
Shower Pan 11/8/2022 Approved BOBBY KEY
Insulation 12/1/2022 Approved HERBERT GIRON
Drywall Nailing 12/7/2022 Approved CLAYTON GRAHAM
Interior/Exterior Lathing 12/7/2022 Partial Approval CLAYTON GRAHAM
BUILDING-Rough-Frame 12/12/2022 Approved BOBBY KEY
Interior/Exterior Lathing 12/12/2022 Approved BOBBY KEY
MERV13>=Rough 12/12/2022 Approved BOBBY KEY
Smoke Detectors 12/12/2022 Partial Approval BOBBY KEY
ELECTRICAL-Final 7/20/2023 Approved BOBBY KEY
Final 7/20/2023 Corrections Issued BOBBY KEY
HVAC-Final 7/20/2023 Approved BOBBY KEY
PLUMBING-Final 7/20/2023 Approved BOBBY KEY
SGSOV-Seismic Gas S/O Valve 7/20/2023 SGSOV Approved BOBBY KEY
Smoke Detectors 7/20/2023 Approved BOBBY KEY
Final 10/25/2023 OK to Issue CofO JESUS RODRIGUEZ
Green Building Final 10/25/2023 Approved JESUS RODRIGUEZ
MERV13>=Final 10/25/2023 Approved JESUS RODRIGUEZ