22916-22918 W OSTRONIC DR 91367
Certificate Information: 22916-22918 W OSTRONIC DR 91367
- Application / Permit
- 22014-20000-00050
- Plan Check / Job No.
- B22VN00144
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- *EPLAN* CONVERT (E) ATTACHED 2-CAR GARAGE TO JADU PER CA GC 65852.2(e)(1)(A) 1 BED 1.5 BATH
- Permit Issued
- Issued on 3/24/2022
- Issuing Office
- Current Status
- CofO Issued on 9/2/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/7/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/9/2022 | VIVIAN LAO |
| Corrections Issued | 1/10/2022 | VIVIAN LAO |
| Applicant returned to address corrections | 2/8/2022 | VIVIAN LAO |
| Applicant returned to address corrections | 3/4/2022 | VIVIAN LAO |
| Applicant returned to address corrections | 3/15/2022 | VIVIAN LAO |
| Plan Check Approved | 3/24/2022 | VIVIAN LAO |
| Issued | 3/24/2022 | APPLICANT |
| CofO in Progress | 9/2/2022 | TROY SANDERS |
| Permit Finaled | 9/2/2022 | JOHN JANSON |
| CofO Issued | 9/2/2022 | JOHN JANSON |
| Permit Finaled | 9/2/2022 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 1/18/2022 | JOSE DUARTE-DIAZ |
| Roof/Waste drainage to street | Cleared | 1/18/2022 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 1/18/2022 | JOSE DUARTE-DIAZ |
| Grading Pre-Inspection | Cleared | 3/4/2022 | VIVIAN LAO |
| Eng Process Fee Ord 176,300 | Cleared | 3/7/2022 | JOSE DUARTE-DIAZ |
Contact Information
| Contractor | All Green Electric Inc; Lic. No.: 947234-B | , |
| Engineer | Gosen,, James W; Lic. No.: C43590 | 15315 BLEDSOE ST SYLMAR, CA 91342 |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/26/2022 | Conditional Approval | DAVID SCANTLIN |
| Footing/Foundation/Slab | 5/9/2022 | Approved | TROY SANDERS |
| PLUMBING-Rough | 5/31/2022 | Partial Approval | TROY SANDERS |
| Interior/Exterior Lathing | 6/6/2022 | Approved | JESUS PINEDA |
| BUILDING-Rough-Frame | 6/10/2022 | Partial Approval | TROY SANDERS |
| ELECTRICAL-Rough | 6/10/2022 | Approved | TROY SANDERS |
| Green Building Rough | 6/10/2022 | Approved | TROY SANDERS |
| HVAC-Rough | 6/10/2022 | Approved | TROY SANDERS |
| MERV13>=Rough | 6/10/2022 | Approved | TROY SANDERS |
| PLUMBING-Rough | 6/10/2022 | Approved | TROY SANDERS |
| Wood Frame | 6/10/2022 | Approved | TROY SANDERS |
| Insulation | 6/14/2022 | Conditional Approval | JESUS PINEDA |
| Shower Pan | 6/14/2022 | Approved | JESUS PINEDA |
| Drywall Nailing | 6/17/2022 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 6/23/2022 | Partial Approval | TROY SANDERS |
| BUILDING-Rough-Frame | 8/12/2022 | Approved | TROY SANDERS |
| ELECTRICAL-Final | 8/12/2022 | Approved | TROY SANDERS |
| Final | 8/12/2022 | Corrections Issued | TROY SANDERS |
| Green Building Final | 8/12/2022 | Approved | TROY SANDERS |
| HVAC-Final | 8/12/2022 | Approved | TROY SANDERS |
| MERV13>=Final | 8/12/2022 | Approved | TROY SANDERS |
| PLUMBING-Final | 8/12/2022 | Approved | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 8/12/2022 | SGSOV Approved | TROY SANDERS |
| Smoke Detectors | 8/12/2022 | Approved | TROY SANDERS |
| Final | 9/2/2022 | OK to Issue CofO | TROY SANDERS |