7325 N CANTALOUPE AVE 91405
Certificate Information: 7325 N CANTALOUPE AVE 91405
- Application / Permit
- 22014-20000-00043
- Plan Check / Job No.
- B22VN00123
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADD IRR SHAPED 15'-8" x 32' TWO-STORY ADDITION AT REAR, ENCLOSE PORTION OF (E) PATIO (26 SF), ENCLOSE PORTION OF (E) PORCH (14 SF), AND REMODEL OF (E) SINGLE FAMILY DWELLING; NFPA 13D FIRE SPRINKLERS REQUIRED; "COMPLY WITH DEPARTMENT ORDER effective date 11/01/2021. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
- Permit Issued
- Issued on 5/31/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 8/3/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/5/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/8/2022 | SEAN SHAHMIRI |
| Corrections Issued | 2/11/2022 | SEAN SHAHMIRI |
| Building Plans Picked Up | 2/17/2022 | APPLICANT |
| Quality Review Completed | 4/5/2022 | STEVEN KIM |
| Plan Check Approved | 4/5/2022 | SEAN SHAHMIRI |
| Issued | 5/31/2022 | APPLICANT |
| CofO in Progress | 7/14/2023 | THOMAS WOODS |
| Permit Finaled | 8/3/2023 | DAVID JAMES |
| CofO Issued | 8/3/2023 | DAVID JAMES |
| Permit Finaled | 8/3/2023 | DAVID JAMES |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/4/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 3/4/2022 | DAGOVERTO GUERRERO |
| Roof/Waste drainage to street | Cleared | 3/23/2022 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Adams,, Robert Charles; Lic. No.: C21234 | 22129 BRYANT STREET CANOGA PARK, CA 91304 |
Inspector Information
| ARA SINANIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HASANTHA WEERASEKARA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| SCOTT SHUSTER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOEL GUARDADO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIYA MIHALEVA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOSE RUBIO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID JAMES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID HICKMAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN HAMILTON, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN STEPHENS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| PIERRE VEGA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK VAN SLOOTEN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MICKEY YAMASHITA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RICHARD ROBLES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HAGOP BADOSSIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| KIM BEAUCHAMP, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK DOVICO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| THOMAS WOODS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAUL VASQUEZ, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| AUGUSTUS ALBAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| FELIPE PENICHE, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| LEO MILBAUER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/6/2022 | Not Ready for Inspection | BRYAN MEYER |
| Excavation/Setback/Form/Re-Bar | 7/8/2022 | Approved | KIM BEAUCHAMP |
| Footing/Foundation/Slab | 7/8/2022 | Approved | KIM BEAUCHAMP |
| Underground Mechanical | 8/30/2022 | Partial Approval | KIM BEAUCHAMP |
| Excavation/Setback/Form/Re-Bar | 10/17/2022 | Approved | BRYAN MEYER |
| BUILDING-Rough-Frame | 1/3/2023 | Not Ready for Inspection | KIM BEAUCHAMP |
| ELECTRICAL-Rough | 1/3/2023 | Not Ready for Inspection | KIM BEAUCHAMP |
| Floor/Roof Diaphrgm/Shear Wall | 1/3/2023 | Partial Approval | KIM BEAUCHAMP |
| HVAC-Rough | 1/3/2023 | Not Ready for Inspection | KIM BEAUCHAMP |
| PLUMBING-Rough | 1/3/2023 | Not Ready for Inspection | KIM BEAUCHAMP |
| BUILDING-Rough-Frame | 1/18/2023 | Corrections Issued | KIM BEAUCHAMP |
| ELECTRICAL-Rough | 1/18/2023 | Corrections Issued | KIM BEAUCHAMP |
| Green Building Rough | 1/18/2023 | Not Ready for Inspection | KIM BEAUCHAMP |
| PLUMBING-Rough | 1/18/2023 | Approved | KIM BEAUCHAMP |
| ELECTRICAL-Rough | 1/20/2023 | Not Ready for Inspection | KIM BEAUCHAMP |
| HVAC-Rough | 1/20/2023 | Not Ready for Inspection | KIM BEAUCHAMP |
| PLUMBING-Rough | 1/20/2023 | Corrections Issued | KIM BEAUCHAMP |
| BUILDING-Rough-Frame | 1/24/2023 | Approved | KIM BEAUCHAMP |
| ELECTRICAL-Rough | 1/24/2023 | Approved | KIM BEAUCHAMP |
| Floor/Roof Diaphrgm/Shear Wall | 1/24/2023 | Approved | KIM BEAUCHAMP |
| Green Building Rough | 1/24/2023 | Approved | KIM BEAUCHAMP |
| PLUMBING-Rough | 1/24/2023 | Approved | KIM BEAUCHAMP |
| Green Building Rough | 1/27/2023 | Approved | KIM BEAUCHAMP |
| HVAC-Rough | 1/27/2023 | Approved | KIM BEAUCHAMP |
| Sewer | 1/27/2023 | Approved | KIM BEAUCHAMP |
| Interior/Exterior Lathing | 2/10/2023 | Approved | KIM BEAUCHAMP |
| Shower Pan | 2/10/2023 | Approved | KIM BEAUCHAMP |
| Interior/Exterior Lathing | 2/23/2023 | Corrections Issued | KIM BEAUCHAMP |
| Interior/Exterior Lathing | 2/28/2023 | Approved | KIM BEAUCHAMP |
| Drywall Nailing | 6/1/2023 | Approved | THOMAS WOODS |
| Final | 6/1/2023 | Not Ready for Inspection | THOMAS WOODS |
| Green Building Final | 6/1/2023 | Corrections Issued | THOMAS WOODS |
| SGSOV-Seismic Gas S/O Valve | 6/1/2023 | SGSOV Not Ready | THOMAS WOODS |
| Smoke Detectors | 6/1/2023 | Not Ready for Inspection | THOMAS WOODS |
| ELECTRICAL-Final | 6/14/2023 | Corrections Issued | THOMAS WOODS |
| Final | 6/14/2023 | Not Ready for Inspection | THOMAS WOODS |
| Green Building Final | 6/14/2023 | Approved | THOMAS WOODS |
| PLUMBING-Final | 6/14/2023 | Corrections Issued | THOMAS WOODS |
| SGSOV-Seismic Gas S/O Valve | 6/14/2023 | SGSOV Approved | THOMAS WOODS |
| Smoke Detectors | 6/14/2023 | Approved | THOMAS WOODS |
| ELECTRICAL-Final | 7/11/2023 | Approved | THOMAS WOODS |
| Final | 7/11/2023 | Conditional Approval | THOMAS WOODS |
| Gas Test | 7/11/2023 | Approved | THOMAS WOODS |
| HVAC-Final | 7/11/2023 | Approved | THOMAS WOODS |
| PLUMBING-Final | 7/11/2023 | Approved | THOMAS WOODS |
| Final | 7/14/2023 | OK to Issue CofO | THOMAS WOODS |