6940-6942 N WYSTONE AVE 91335
Certificate Information: 6940-6942 N WYSTONE AVE 91335
- Application / Permit
- 22014-20000-00038
- Plan Check / Job No.
- B22VN00100
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E)20'-0"' X 20'-3" ATTACHED GARAGE TO ACCESSORY DWELLING UNIT (ADU) AND ADD 6' X 13'-7", ADD 9'-1" X 23'-1" TO THE BACK OF THE SFD, AND REMODEL TO (E) SFD.
- Permit Issued
- Issued on 2/23/2022
- Issuing Office
- Current Status
- CofO Issued on 8/11/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/4/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/21/2022 | RAPHAEL ROSAS |
| Corrections Issued | 1/22/2022 | RAPHAEL ROSAS |
| Building Plans Picked Up | 1/27/2022 | APPLICANT |
| Plan Check Approved | 2/10/2022 | MOHAMMAD ESMAILI |
| Issued | 2/23/2022 | APPLICANT |
| CofO in Progress | 7/25/2022 | JEFFREY BULL |
| Permit Finaled | 8/11/2022 | JOHN JANSON |
| CofO Issued | 8/11/2022 | JOHN JANSON |
| Permit Finaled | 8/11/2022 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 2/1/2022 | AMIR KASHFI |
| Roof/Waste drainage to street | Cleared | 2/1/2022 | AMIR KASHFI |
| ZI | Cleared | 2/1/2022 | MIGUEL GAMBOA |
| Eng Process Fee Ord 176,300 | Cleared | 2/2/2022 | AMIR KASHFI |
| Sewer availability | Cleared | 2/3/2022 | AMIR KASHFI |
Contact Information
| Contractor | Platinum Home Remodeling Inc; Lic. No.: 1060535-B | 12444 VICTORY BLVD #402 VALLEY GLEN, CA 91606 |
| Engineer | Wu,, Harold Ping-Hung; Lic. No.: C35693 | 1168 SAN GABRIEL BLVD NO N ROSEMEAD, CA 91770 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 2/28/2022 | Approved | VINCENT HANLEY |
| Footing/Foundation/Slab | 2/28/2022 | Corrections Issued | VINCENT HANLEY |
| Excavation/Setback/Form/Re-Bar | 3/7/2022 | Approved | VINCENT HANLEY |
| Footing/Foundation/Slab | 3/7/2022 | Approved | VINCENT HANLEY |
| Insulation | 3/15/2022 | Partial Approval | VINCENT HANLEY |
| Shower Pan | 3/15/2022 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 3/25/2022 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 4/1/2022 | Partial Approval | VINCENT HANLEY |
| ELECTRICAL-Rough | 4/1/2022 | Approved | VINCENT HANLEY |
| Green Building Rough | 4/1/2022 | Not Ready for Inspection | VINCENT HANLEY |
| PLUMBING-Rough | 4/1/2022 | Approved | VINCENT HANLEY |
| Rough-Elec/Plmb/HVAC | 4/1/2022 | Approved | VINCENT HANLEY |
| Insulation | 4/6/2022 | Partial Approval | VINCENT HANLEY |
| Interior/Exterior Lathing | 4/6/2022 | Partial Approval | VINCENT HANLEY |
| Insulation | 4/8/2022 | Not Ready for Inspection | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 4/8/2022 | Partial Approval | JUSTIN HAWLEY |
| Drywall Nailing | 4/12/2022 | Partial Inspection | KRISTEN CAUSEY |
| Insulation | 4/12/2022 | Approved | KRISTEN CAUSEY |
| Drywall Nailing | 4/15/2022 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 4/15/2022 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 4/15/2022 | Partial Approval | VINCENT HANLEY |
| Interior/Exterior Lathing | 4/26/2022 | Approved | MORRIS JACKSON |
| Shower Pan | 4/26/2022 | Approved | MORRIS JACKSON |
| Shower Pan | 5/6/2022 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 6/24/2022 | Approved | VINCENT HANLEY |
| Final | 6/24/2022 | Corrections Issued | VINCENT HANLEY |
| Green Building Final | 6/24/2022 | Approved | VINCENT HANLEY |
| Green Building Rough | 6/24/2022 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 6/24/2022 | SGSOV Approved | VINCENT HANLEY |
| Smoke Detectors | 6/24/2022 | Approved | VINCENT HANLEY |
| Final | 7/22/2022 | OK to Issue CofO | JEFFREY BULL |