7823 N ST CLAIR AVE 91605
Certificate Information: 7823 N ST CLAIR AVE 91605
- Application / Permit
- 22014-20000-00024
- Plan Check / Job No.
- B22VN00045
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 18'-1" X 20'-1" DETACHED GARAGE AND ADD 19'-5" X 42'-7" IRREGULAR SHAPE INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d).
- Permit Issued
- Issued on 5/2/2022
- Issuing Office
- Current Status
- CofO Issued on 10/12/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/3/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/14/2022 | RAPHAEL ROSAS |
| Corrections Issued | 1/16/2022 | RAPHAEL ROSAS |
| Building Plans Picked Up | 1/20/2022 | APPLICANT |
| Plan Check Approved | 4/23/2022 | MOHAMMAD ESMAILI |
| Issued | 5/2/2022 | APPLICANT |
| CofO in Progress | 10/7/2022 | CHRISTOPHER DELLEFIELD |
| CofO Issued | 10/12/2022 | MICHAEL SMITH |
| Permit Finaled | 10/12/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 1/31/2022 | AMIR KASHFI |
| Eng Process Fee Ord 176,300 | Cleared | 2/1/2022 | AMIR KASHFI |
| Sewer availability | Cleared | 2/1/2022 | AMIR KASHFI |
| Low Impact Development | Cleared | 3/15/2022 | TA ANH |
| Construction near power lines | Cleared | 4/13/2022 | RIDWAN HARDY |
| Roof/Waste drainage to street | Cleared | 4/14/2022 | ABDULLAH SADOZAI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| MATTHEW NELSON, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 6/6/2022 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Excavation/Setback/Form/Re-Bar | 6/14/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Footing/Foundation/Slab | 6/14/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 7/6/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 7/6/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Deputy Wood Construction | 7/7/2022 | No Result Entered | ADRIAN GAUTHIER |
| ELECTRICAL-Rough | 7/8/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 7/8/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 7/8/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 7/8/2022 | Partial Approval | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 7/18/2022 | Corrections Issued | JENNIFER RABUCHIN |
| HVAC-Rough | 7/18/2022 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 7/18/2022 | Approved | JENNIFER RABUCHIN |
| Sewer | 7/18/2022 | Partial Approval | JENNIFER RABUCHIN |
| Underground Mechanical | 7/18/2022 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 7/20/2022 | Conditional Approval | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 7/25/2022 | Approved | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 7/25/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 7/25/2022 | Approved | CHRISTOPHER DELLEFIELD |
| HVAC-Rough | 7/25/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Insulation | 7/27/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Shower Pan | 7/27/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Drywall Nailing | 8/1/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Insulation | 8/1/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 8/1/2022 | Approved | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Final | 9/26/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Final | 9/26/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Green Building Final | 9/26/2022 | Approved | CHRISTOPHER DELLEFIELD |
| HVAC-Final | 9/26/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| PLUMBING-Final | 9/26/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| SGSOV-Seismic Gas S/O Valve | 9/26/2022 | SGSOV Approved | CHRISTOPHER DELLEFIELD |
| Smoke Detectors | 9/26/2022 | Approved | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Final | 10/7/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Final | 10/7/2022 | OK to Issue CofO | CHRISTOPHER DELLEFIELD |
| HVAC-Final | 10/7/2022 | Approved | CHRISTOPHER DELLEFIELD |
| PLUMBING-Final | 10/7/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Service/Power Release | 10/7/2022 | Approved | CHRISTOPHER DELLEFIELD |