3905-3907 S HARVARD BLVD 90062
Certificate Information: 3905-3907 S HARVARD BLVD 90062
- Application / Permit
- 22014-20000-00023
- Plan Check / Job No.
- B22VN00044
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- FIRE DAMAGE REBUILD, MAJOR REMODEL, REMOVE (E) PATIO COVER, CONVERT (E) ATT. REC ROOM TO (N) ACCESSORY DWELLING UNIT AND ADD 14'-9" x 19'-4" TO ADU PER LAMC 12.22 A.33(c) and (e); AUTOMATIC SPRINKLER SYSTEM IS REQ'D
- Permit Issued
- Issued on 3/7/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/14/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/3/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/4/2022 | SEAN SHAHMIRI |
| Corrections Issued | 2/7/2022 | SEAN SHAHMIRI |
| Quality Review Completed | 2/17/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 2/18/2022 | APPLICANT |
| Applicant returned to address corrections | 7/20/2022 | SEAN SHAHMIRI |
| Plan Check Approved | 8/25/2022 | SEAN SHAHMIRI |
| Issued | 3/7/2023 | APPLICANT |
| CofO in Progress | 6/11/2025 | SABAS ALONSO |
| Permit Finaled | 6/14/2025 | DEROLD HAUFF |
| CofO Issued | 6/14/2025 | DEROLD HAUFF |
| Permit Finaled | 6/14/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 2/16/2022 | WALLIE JONG |
| Roof/Waste drainage to street | Cleared | 2/16/2022 | WALLIE JONG |
| Low Impact Development | Cleared | 3/14/2022 | ANTHONY VARGAS |
| Eng Process Fee Ord 176,300 | Cleared | 5/17/2022 | WALLIE JONG |
| Sewer availability | Cleared | 5/17/2022 | WALLIE JONG |
Contact Information
| Contractor | Pro Build Inc; Lic. No.: 1005294-B | 2321 1/2 S RIDGELEY DR LOS ANGELES, CA 90016 |
| Engineer | Rhee,, Kyle; Lic. No.: C78215 | 2753 WAVERLY DR 403 LOS ANGELES, CA 90039 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/17/2023 | Partial Inspection | SABAS ALONSO |
| Footing/Foundation/Slab | 5/15/2023 | Partial Approval | SABAS ALONSO |
| Excavation/Setback/Form/Re-Bar | 5/19/2023 | Approved | SABAS ALONSO |
| Footing/Foundation/Slab | 5/19/2023 | Approved | SABAS ALONSO |
| Insulation | 7/13/2023 | Not Ready for Inspection | SABAS ALONSO |
| Sewer | 7/13/2023 | Approved | SABAS ALONSO |
| Underground Mechanical | 7/13/2023 | Partial Approval | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 7/26/2023 | Partial Approval | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 10/24/2023 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 5/7/2024 | Not Ready for Inspection | SABAS ALONSO |
| ELECTRICAL-Rough | 5/7/2024 | Approved | SABAS ALONSO |
| Green Building Rough | 5/7/2024 | Corrections Issued | SABAS ALONSO |
| HVAC-Rough | 5/7/2024 | Approved | SABAS ALONSO |
| PLUMBING-Rough | 5/7/2024 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 6/6/2024 | Corrections Issued | SABAS ALONSO |
| Interior/Exterior Lathing | 6/6/2024 | Partial Approval | SABAS ALONSO |
| Shower Pan | 6/6/2024 | Approved | SABAS ALONSO |
| Green Building Rough | 6/10/2024 | Approved | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 6/10/2024 | Approved | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 7/1/2024 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 7/1/2024 | Approved | SABAS ALONSO |
| Verify Sprinkler Sign Off | 7/1/2024 | Approved | SABAS ALONSO |
| Insulation | 7/10/2024 | Approved | SABAS ALONSO |
| Drywall Nailing | 7/16/2024 | Approved | SABAS ALONSO |
| ELECTRICAL-Final | 3/25/2025 | Approved | SABAS ALONSO |
| Final | 3/25/2025 | Not Ready for Inspection | SABAS ALONSO |
| Gas Test | 3/25/2025 | Approved | SABAS ALONSO |
| Green Building Final | 3/25/2025 | Approved | SABAS ALONSO |
| HVAC-Final | 3/25/2025 | Approved | SABAS ALONSO |
| PLUMBING-Final | 3/25/2025 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 3/25/2025 | SGSOV Approved | SABAS ALONSO |
| Service/Power Release | 3/25/2025 | Not Ready for Inspection | SABAS ALONSO |
| Smoke Detectors | 3/25/2025 | Approved | SABAS ALONSO |
| Final | 5/2/2025 | Not Ready for Inspection | SABAS ALONSO |
| Service/Power Release | 5/2/2025 | Not Ready for Inspection | SABAS ALONSO |
| Final | 6/10/2025 | OK to Issue CofO | SABAS ALONSO |
| Service/Power Release | 6/10/2025 | Approved | SABAS ALONSO |