10120-10122 N SHOSHONE AVE 91325
Certificate Information: 10120-10122 N SHOSHONE AVE 91325
- Application / Permit
- 22014-20000-00009
- Plan Check / Job No.
- B22VN00023
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- *EPLAN* CONVERT (E) ATTACHED 2-CAR GARAGE TO ADU PER LAMC 12.22.A.33(c) AND (e). CONVERT PORTION OF SFD TO ADU ADD AT REAR TO ADU ALL WORK PER W.F.P.P.
- Permit Issued
- Issued on 1/18/2022
- Issuing Office
- Current Status
- CofO Issued on 8/2/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/3/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/3/2022 | VIVIAN LAO |
| Corrections Issued | 1/4/2022 | VIVIAN LAO |
| Plan Check Approved | 1/11/2022 | VIVIAN LAO |
| Issued | 1/18/2022 | APPLICANT |
| CofO in Progress | 7/28/2022 | ROBERT GOLD |
| Permit Finaled | 8/2/2022 | DANIEL ORRANTE |
| CofO Issued | 8/2/2022 | DANIEL ORRANTE |
| Permit Finaled | 8/2/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 1/6/2022 | AMIR KASHFI |
| Roof/Waste drainage to street | Cleared | 1/6/2022 | AMIR KASHFI |
| Eng Process Fee Ord 176,300 | Cleared | 1/7/2022 | AMIR KASHFI |
| Sewer availability | Cleared | 1/7/2022 | AMIR KASHFI |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 1/21/2022 | Approved | JESUS RODRIGUEZ |
| Sewer | 1/21/2022 | Approved | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 1/25/2022 | Approved | DEANDRE HOFFMAN |
| BUILDING-Rough-Frame | 2/7/2022 | Corrections Issued | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 2/7/2022 | Approved | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 2/7/2022 | Approved | JESUS RODRIGUEZ |
| Green Building Rough | 2/7/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| HVAC-Rough | 2/7/2022 | Corrections Issued | JESUS RODRIGUEZ |
| PLUMBING-Rough | 2/7/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 2/10/2022 | Partial Approval | RAUL OLAGI |
| Insulation | 2/10/2022 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 2/10/2022 | Partial Approval | RAUL OLAGI |
| BUILDING-Rough-Frame | 2/16/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Drywall Nailing | 2/16/2022 | Approved | JESUS RODRIGUEZ |
| Green Building Rough | 2/16/2022 | Approved | JESUS RODRIGUEZ |
| HVAC-Rough | 2/16/2022 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Rough | 2/16/2022 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 2/17/2022 | Approved | JESUS RODRIGUEZ |
| Pre-Inspection | 2/17/2022 | Approved | MICHAEL TEMPLE |
| Shower Pan | 2/17/2022 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 3/24/2022 | Approved | RAUL OLAGI |
| Final | 3/24/2022 | Corrections Issued | RAUL OLAGI |
| Green Building Final | 3/24/2022 | Approved | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 3/24/2022 | SGSOV Approved | RAUL OLAGI |
| Smoke Detectors | 3/24/2022 | Approved | RAUL OLAGI |
| ELECTRICAL-Final | 3/31/2022 | Approved | RAUL OLAGI |
| Final | 3/31/2022 | Corrections Issued | RAUL OLAGI |
| HVAC-Final | 3/31/2022 | Approved | RAUL OLAGI |
| PLUMBING-Final | 3/31/2022 | Approved | RAUL OLAGI |
| Final | 7/28/2022 | OK to Issue CofO | ROBERT GOLD |