13375 W GAGER ST 91331

Certificate Information: 13375 W GAGER ST 91331

Application / Permit
22014-20000-00005
Plan Check / Job No.
B21VN18178
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: (N) ADDITION TO CONNECT (E) STORAGE AND (E) GARAGE AND CONVERT THE (E) STORAGE AND (N) ADDITION TO ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33.(c)-(d)
Permit Issued
Issued on 5/5/2022
Issuing Office
Current Status
CofO Issued on 2/9/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/5/2022 APPLICANT
Assigned to Plan Check Engineer 1/5/2022 DANIEL YIP
Corrections Issued 1/6/2022 DANIEL YIP
Plan Check Approved 4/29/2022 DANIEL YIP
Issued 5/5/2022 APPLICANT
CofO in Progress 2/7/2023 MICHEL ABAJAN
Permit Finaled 2/9/2023 RONALD MYRICK
CofO Issued 2/9/2023 RONALD MYRICK
Permit Finaled 2/9/2023 RONALD MYRICK

Permit Application Clearance Information

Address approval Cleared 2/9/2022 CARLOS AGUILERA
Clean Up Green Up Cleared 2/9/2022 LAUREN PADICK
Roof/Waste drainage to street Cleared 2/9/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 3/9/2022 CARLOS AGUILERA
Sewer availability Cleared 3/9/2022 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/10/2022 Partial Approval MICHEL ABAJAN
Deputy Drilled-In Anchors 8/16/2022 Approved MICHEL ABAJAN
Footing/Foundation/Slab 8/22/2022 Approved JENNIFER RABUCHIN
METHANE-Barrier 8/22/2022 Approved JENNIFER RABUCHIN
METHANE-Subgrade 8/22/2022 Approved JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 9/13/2022 Partial Approval MICHEL ABAJAN
BUILDING-Rough-Frame 10/14/2022 Approved MICHEL ABAJAN
ELECTRICAL-Rough 10/14/2022 Approved MICHEL ABAJAN
Green Building Rough 10/14/2022 Approved MICHEL ABAJAN
HVAC-Rough 10/14/2022 Approved MICHEL ABAJAN
METHANE-Rough 10/14/2022 Approved MICHEL ABAJAN
PLUMBING-Rough 10/14/2022 Approved MICHEL ABAJAN
Underground Mechanical 10/14/2022 Approved MICHEL ABAJAN
Insulation 10/27/2022 Approved MICHEL ABAJAN
Interior/Exterior Lathing 10/27/2022 Approved MICHEL ABAJAN
Drywall Nailing 11/14/2022 Approved MICHEL ABAJAN
Interior/Exterior Lathing 11/14/2022 Approved MICHEL ABAJAN
ELECTRICAL-Final 1/6/2023 Corrections Issued MICHEL ABAJAN
Final 1/6/2023 Corrections Issued MICHEL ABAJAN
Green Building Final 1/6/2023 Not Ready for Inspection MICHEL ABAJAN
HVAC-Final 1/6/2023 Corrections Issued MICHEL ABAJAN
PLUMBING-Final 1/6/2023 Corrections Issued MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 1/6/2023 SGSOV Not Ready MICHEL ABAJAN
Smoke Detectors 1/6/2023 Not Ready for Inspection MICHEL ABAJAN
ELECTRICAL-Final 2/7/2023 Approved MICHEL ABAJAN
Final 2/7/2023 OK to Issue CofO MICHEL ABAJAN
Green Building Final 2/7/2023 Approved MICHEL ABAJAN
HVAC-Final 2/7/2023 Approved MICHEL ABAJAN
PLUMBING-Final 2/7/2023 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 2/7/2023 SGSOV Approved MICHEL ABAJAN
Smoke Detectors 2/7/2023 Approved MICHEL ABAJAN