1305-1305 1/2 W GRANT ST 90744
Certificate Information: 1305-1305 1/2 W GRANT ST 90744
- Application / Permit
- 22014-10002-02276
- Plan Check / Job No.
- B24LA00779
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan - supplemental to 22014-10000-02276 to update scope of work from alteration/addition to new construction, no change to floor area
- Permit Issued
- Issued on 6/10/2024
- Issuing Office
- Current Status
- Permit Finaled on 6/3/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/17/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/1/2024 | KELVIN CHUONG |
| Corrections Issued | 2/3/2024 | KELVIN CHUONG |
| Quality Review Completed | 2/14/2024 | RODOLFO ARIAS |
| Applicant returned to address corrections | 2/22/2024 | KELVIN CHUONG |
| Applicant returned to address corrections | 5/9/2024 | KELVIN CHUONG |
| Plan Check Approved | 6/10/2024 | KELVIN CHUONG |
| Issued | 6/10/2024 | APPLICANT |
| Permit Finaled | 6/3/2025 | EUGENE CASSIDY |
Permit Application Clearance Information
| Low Impact Development (LID) | Cleared | 3/22/2024 | TOMMY YIN |
| Eng Process Fee Ord 176,300 | Cleared | 5/22/2024 | JILVER MAZARIEGOS |
| Roof/Waste drainage to street | Cleared | 5/22/2024 | JILVER MAZARIEGOS |
| Sewer availability | Cleared | 5/22/2024 | JILVER MAZARIEGOS |
| Construction near power lines | Cleared | 5/23/2024 | EDGAR PASCUA |
| Senate Bill 9 | Cleared | 5/28/2024 | FIPE LEILUA |
| Hydrant and Access approval | Cleared | 6/5/2024 | GILBERT URREA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 11/8/2024 | Corrections Issued | EUGENE CASSIDY |
| MERV13>=Rough | 11/8/2024 | Approved | EUGENE CASSIDY |
| Deputy Wood Construction | 11/13/2024 | Partial Approval | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 11/19/2024 | Approved | ANSON MAGLASANG |
| Drywall Nailing | 12/5/2024 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 12/5/2024 | Partial Approval | EUGENE CASSIDY |
| Final | 2/6/2025 | Not Ready for Inspection | EUGENE CASSIDY |
| MERV13>=Final | 2/6/2025 | Not Ready for Inspection | EUGENE CASSIDY |
| Smoke Detectors | 2/6/2025 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 5/14/2025 | Corrections Issued | EUGENE CASSIDY |
| MERV13>=Final | 5/14/2025 | Not Ready for Inspection | EUGENE CASSIDY |
| Smoke Detectors | 5/14/2025 | Approved | EUGENE CASSIDY |
| Final | 6/3/2025 | Permit Finaled | EUGENE CASSIDY |
| MERV13>=Final | 6/3/2025 | Approved | EUGENE CASSIDY |