4364 S WESTLAWN AVE 90066
Certificate Information: 4364 S WESTLAWN AVE 90066
- Application / Permit
- 22014-10002-01813
- Plan Check / Job No.
- B25LA36666
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Supplemental Ref to #22014-10000-01813 for revisions to include "Replacement of termite/water-damaged framing, cracked slab on grade, and deficient footings. East half of roof reframed (gable) with upgraded 2x6 @ 16" o.c. rafters. North wall framing revised for new footing; south garage footing stabilized with pad underpinnings. Roof details updated for deeper rafters, higher R-value insulation, clarified sheathing and polish slab (no tile), omit BBQ/east gravel, driveway paving to poured concrete. Two damaged skylights replaced with Velux; revised Title 24 reflects skylights, roof, and NFRC values."
- Permit Issued
- Issued on 9/11/2025
- Issuing Office
- Current Status
- Permit Finaled on 4/7/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/2/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 9/4/2025 | DAVID CASTILLO |
| Corrections Issued | 9/5/2025 | DAVID CASTILLO |
| Plan Check Approved | 9/10/2025 | CAROLEAN BASMA |
| Issued | 9/11/2025 | APPLICANT |
| Permit Finaled-Status Void | 3/31/2026 | ANTHONY EGSON |
| Permit Finaled | 3/31/2026 | ANTHONY EGSON |
| Re-Activate Permit | 4/7/2026 | ANTHONY EGSON |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 9/8/2025 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 9/9/2025 | TREVOR QUAN |
Contact Information
| Architect | Holden,, Clay Franklin; Lic. No.: NA31098 | , |
| Contractor | W A Construction Inc; Lic. No.: 1024282-B | , |
| Engineer | Paniagua,, Cristobal; Lic. No.: NA72894 | , |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/19/2025 | Corrections Issued | HERBERT GIRON |
| Footing/Foundation/Slab | 9/19/2025 | Corrections Issued | HERBERT GIRON |
| Final | 3/31/2026 | Permit Finaled | ANTHONY EGSON |