1801 S WOOSTER ST 90035
Certificate Information: 1801 S WOOSTER ST 90035
- Application / Permit
- 22014-10001-05605
- Plan Check / Job No.
- B23LA05972
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan Supplemental Permit# 22014-10000-05605 for ADU Addition including Conversion of Garage and Bedroom addition into attached 880sf 1-Story ADU (Type VB R-3 Occupancy).PER LAMC 12.22 A.33(c) AND (e)
- Permit Issued
- Issued on 5/12/2023
- Issuing Office
- Current Status
- Permit Finaled on 12/2/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/3/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/6/2023 | ALFREDO JARA |
| Corrections Issued | 4/10/2023 | ALFREDO JARA |
| Plan Check Approved | 5/12/2023 | AMY GUEVARRA |
| Issued | 5/12/2023 | APPLICANT |
| Permit Finaled | 12/1/2023 | MEL KHACHATOURIAN |
Permit Application Clearance Information
| Low Impact Development (LID) | Cleared | 4/19/2023 | ROGELIO CORTES |
| Address approval | Cleared | 4/21/2023 | TREVOR QUAN |
| Roof/Waste drainage to street | Cleared | 4/21/2023 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 4/24/2023 | TREVOR QUAN |
| Sewer availability | Cleared | 4/24/2023 | TREVOR QUAN |
Contact Information
| Architect | Stockton,, Richard Kenneth; Lic. No.: NA35492 | , |
| Contractor | Owner-Builder | , |
| Engineer | Van, Elden, Alexander Craig; Lic. No.: C71696 | 2415 FORDHAM DR COSTA MESA, CA 92626 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/19/2023 | Partial Approval | JEREMY TODD |
| Footing/Foundation/Slab | 5/25/2023 | Not Ready for Inspection | JEREMY TODD |
| METHANE-Barrier | 5/25/2023 | Not Ready for Inspection | JEREMY TODD |
| METHANE-Subgrade | 5/25/2023 | Not Ready for Inspection | JEREMY TODD |
| METHANE-Subgrade | 5/30/2023 | Corrections Issued | JEREMY TODD |
| METHANE-Subgrade | 6/2/2023 | Approved | JEREMY TODD |
| Footing/Foundation/Slab | 6/5/2023 | Approved | JEREMY TODD |
| METHANE-Barrier | 6/5/2023 | Approved | JEREMY TODD |
| Floor/Roof Diaphrgm/Shear Wall | 6/23/2023 | Not Ready for Inspection | JEREMY TODD |
| Insulation | 6/23/2023 | Partial Approval | JEREMY TODD |
| PLUMBING-Rough | 6/23/2023 | Partial Approval | JEREMY TODD |
| Deputy Drilled-In Anchors | 7/12/2023 | Conditional Approval | ARAM AVEDISIAN |
| Deputy Wood Construction | 7/12/2023 | Conditional Approval | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 7/13/2023 | Corrections Issued | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/13/2023 | Partial Approval | ARAM AVEDISIAN |
| Gas Test | 7/13/2023 | Partial Approval | ARAM AVEDISIAN |
| Rough-Elec/Plmb/HVAC | 7/13/2023 | Partial Approval | ARAM AVEDISIAN |
| Deputy Wood Construction | 7/20/2023 | Conditional Approval | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 7/21/2023 | Not Ready for Inspection | ARAM AVEDISIAN |
| HVAC-Rough | 7/21/2023 | Corrections Issued | ARAM AVEDISIAN |
| METHANE-Rough | 7/21/2023 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 7/28/2023 | Corrections Issued | ARAM AVEDISIAN |
| HVAC-Rough | 7/28/2023 | Corrections Issued | ARAM AVEDISIAN |
| Insulation | 7/28/2023 | Corrections Issued | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 7/28/2023 | Partial Approval | ARAM AVEDISIAN |
| METHANE-Rough | 7/28/2023 | Corrections Issued | ARAM AVEDISIAN |
| HVAC-Rough | 8/1/2023 | Approved | ARAM AVEDISIAN |
| Shower Pan | 8/1/2023 | Approved | ARAM AVEDISIAN |
| Drywall Nailing | 8/4/2023 | Approved | ARAM AVEDISIAN |
| METHANE-Rough | 8/4/2023 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 8/8/2023 | Partial Approval | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 11/21/2023 | Approved | MEL KHACHATOURIAN |
| Final | 11/21/2023 | Corrections Issued | MEL KHACHATOURIAN |
| Smoke Detectors | 11/21/2023 | Approved | MEL KHACHATOURIAN |
| Final | 11/29/2023 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Gas Test | 11/29/2023 | Approved | MEL KHACHATOURIAN |
| Final | 12/1/2023 | Permit Finaled | MEL KHACHATOURIAN |