130 S ALVARADO ST 90057

Certificate Information: 130 S ALVARADO ST 90057

Application / Permit
22014-10001-05394
Plan Check / Job No.
B23LA06187
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Medical Clinic
Work Description
ePlan: ***SUPPLEMENTLA TO PERMIT 22014-10000-05394 SCOPE OF WORK: INFILL THE EXISTING UNEVEN SLAB WITH LIGHT WEIGHT CONCRETE FOR AN EVEN FLOOR SURFACE ON LEVEL ONE OF THE BUILDING. SCOPE ALSO INCLUDES PROVISION OF STRUCTURAL REINFORCEMMENT AT THE BASEMENT LEVEL TO SUPPORT THE ADDED WEIGHT
Permit Issued
Issued on 5/18/2023
Issuing Office
Current Status
Permit Finaled on 1/10/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/5/2023 APPLICANT
Assigned to Plan Check Engineer 4/13/2023 SINA KHOSRAVI
Corrections Issued 4/20/2023 SINA KHOSRAVI
Quality Review Completed 4/25/2023 TEODORO DIAZ RODRIGUEZ
Plan Check Approved 5/9/2023 SINA KHOSRAVI
Issued 5/18/2023 APPLICANT
Permit Finaled 1/10/2024 KATY RAMIREZ

Permit Application Clearance Information

DAS Clearance Cleared 4/25/2023 Ricardo Ramirez Solis

Contact Information

Architect Morris,, Peter Lloyd; Lic. No.: NA32096       ,
Contractor Bergman Build,Llc; Lic. No.: 982577-B       ,
Engineer Chen,, Jeff Ying-Chih; Lic. No.: S4699 17500 REDHILL AVENUE SUITE 240      IRVINE, CA 92614

Inspector Information

JEROME BLACKWOOD, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI
REGINA MENDEZ, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Structural Steel Frame 7/28/2023 Partial Approval LARRY ARNICK
Excavation/Setback/Form/Re-Bar 7/31/2023 Partial Approval KATY RAMIREZ
Structural Steel Frame 7/31/2023 Partial Inspection KATY RAMIREZ
Final 9/11/2023 Not Ready for Inspection RAMAZANALI ALMASI
Smoke Detectors 9/11/2023 Not Ready for Inspection RAMAZANALI ALMASI
Final 9/18/2023 Partial Inspection KATY RAMIREZ