12310 W 1ST HELENA DR 90049

Certificate Information: 12310 W 1ST HELENA DR 90049

Application / Permit
22014-10001-04294
Plan Check / Job No.
B23LA04645
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
SUPPLEMENTAL TO 22014-10000-04294 Revise and remodel approval floor plan layout on 1st and 2nd floor. See Comment.
Permit Issued
Issued on 4/10/2023
Issuing Office
Metro
Current Status
Permit Finaled on 1/9/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/16/2023 APPLICANT
Assigned to Plan Check Engineer 3/16/2023 TSE MING HUANG
Corrections Issued 3/18/2023 TSE MING HUANG
Quality Review Completed 3/21/2023 KEN GILL
Building Plans Picked Up 3/22/2023 APPLICANT
Plan Check Approved 4/7/2023 TSE MING HUANG
Issued 4/10/2023 APPLICANT
Permit Finaled 1/9/2024 ARAM AVEDISIAN

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/29/2023 DINAH GARIN
Low Impact Development (LID) Cleared 4/5/2023 TOMMY YIN
Roof/Waste drainage to street Cleared 4/6/2023 ANTHONY MAINEZ

Contact Information

Architect Hadaegh,, Reza A; Lic. No.: C25803 5347 BINDEWALD RD.      TORRANCE, CA 90505
Architect Noteware,, Brian Arthur; Lic. No.: C21514 845 20TH STREET, #106      SANTA MONICA, CA 90403
Contractor Barani Construction Inc; Lic. No.: 1001764-B 3093 MILESTONE AVE      SIMI VALLEY, CA 93065

Inspector Information

HERBERT GIRON, (310) 914-3891 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/12/2023 Partial Inspection OGANES TARAKHCHYAN
Deputy Drilled-In Anchors 4/18/2023 No Access for Inspection KENNETH NAGLE
Footing/Foundation/Slab 4/19/2023 Corrections Issued STEPHANIE SWANSON
Excavation/Setback/Form/Re-Bar 4/21/2023 Partial Approval BRENDAN LOONEY
Footing/Foundation/Slab 6/7/2023 Corrections Issued OGANES TARAKHCHYAN
Footing/Foundation/Slab 6/8/2023 Corrections Issued OGANES TARAKHCHYAN
Special/Order Compliance 6/8/2023 Corrections Issued OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 6/16/2023 Partial Approval KENNETH NAGLE
Floor/Roof Diaphrgm/Shear Wall 6/27/2023 Approved OGANES TARAKHCHYAN
Footing/Foundation/Slab 6/27/2023 Approved OGANES TARAKHCHYAN
Special/Order Compliance 6/27/2023 Corrections Issued OGANES TARAKHCHYAN
Interior/Exterior Lathing 7/5/2023 Corrections Issued STEPHANIE SWANSON
Insulation 7/7/2023 Partial Approval OGANES TARAKHCHYAN
Interior/Exterior Lathing 7/7/2023 Partial Approval OGANES TARAKHCHYAN
Drywall Nailing 7/13/2023 Partial Approval OGANES TARAKHCHYAN
BUILDING-Rough-Frame 8/3/2023 Partial Approval HERBERT GIRON
Green Building Rough 8/3/2023 Not Ready for Inspection HERBERT GIRON
Interior/Exterior Lathing 8/14/2023 Partial Inspection KEVIN SARGSYAN