1673 W HILL DR 90041

Certificate Information: 1673 W HILL DR 90041

Application / Permit
22014-10001-03391
Plan Check / Job No.
B23LA12862
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan SUPPLEMETAL TO 22014-10000-03391 TO REVISE ADDITIONS AND CONVERSIONS NEW MASTER BEDROOM ADDITION (215 SQ. FT.) NEW ADDITION (76 SQ. FT.) NEW REAR PORCH (18 SQ. FT.) INTERIOR REMODEL (E) KITCHEN & FAMILY ROOM (E) PATIO TO BE CONVERTED INTO S.F.D. (24 SQ. FT.) (E) PATIO TO BE CONVERTED INTO SUNROOM (69 SQ. FT.) Pervious Scope of work NEW ADDITION (247 SQ. FT.) - NEW FAMILY ROOM, BATH & LAUNDRY INTERIOR REMODELED - NEW BEDROOM & KITCHEN (504 SQ. FT.) PATIO TO BE CONVERTED INTO SUNROOM (93 SQ. FT.)
Permit Issued
Issued on 12/12/2023
Issuing Office
Current Status
Permit Finaled on 9/16/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/13/2023 APPLICANT
Assigned to Plan Check Engineer 7/13/2023 MINA HABILI
Corrections Issued 7/14/2023 MINA HABILI
Applicant returned to address corrections 10/29/2023 ZAW HAN
Plan Check Approved 11/14/2023 ZAW HAN
Issued 12/12/2023 APPLICANT
Permit Finaled 9/13/2024 ROY SPAULDING

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Christopher Williams; Lic. No.: 711380-B       ,
Contractor Williams Christopher; Lic. No.: 711380-B       ,
Engineer Wu,, Harold Ping-Hung; Lic. No.: NA35693       ,

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/31/2024 Approved CRAIG VAUGHAN
BUILDING-Rough-Frame 3/28/2024 Partial Approval CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 3/28/2024 Partial Approval CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 4/3/2024 Partial Approval CRAIG VAUGHAN
Deputy Wood Construction 4/4/2024 Conditional Approval CRAIG VAUGHAN
ELECTRICAL-Rough 4/22/2024 Corrections Issued CRAIG VAUGHAN
HVAC-Rough 4/22/2024 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 4/22/2024 Not Ready for Inspection CRAIG VAUGHAN
Wood Frame 4/22/2024 Not Ready for Inspection CRAIG VAUGHAN
BUILDING-Rough-Frame 4/30/2024 Approved ALIZAH MAYAGOITIA
ELECTRICAL-Rough 4/30/2024 Approved ALIZAH MAYAGOITIA
Green Building Rough 4/30/2024 Approved ALIZAH MAYAGOITIA
Interior/Exterior Lathing 4/30/2024 Approved ALIZAH MAYAGOITIA
Insulation 5/7/2024 Approved CRAIG VAUGHAN
Drywall Nailing 5/14/2024 Approved JOSH MEISTER
Final 9/13/2024 Permit Finaled ROY SPAULDING
Green Building Final 9/13/2024 Approved ROY SPAULDING