9402 W BEVERLYCREST DR 90210

Certificate Information: 9402 W BEVERLYCREST DR 90210

Application / Permit
22014-10001-02686
Plan Check / Job No.
B24LA05775
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
*EPLAN* SUPPLEMENTAL PERMIT TO 22014-10000-02686 REDUCE ADDITION AND REVISE FLOOR PLAN. NFPA 13D
Permit Issued
Issued on 9/9/2024
Issuing Office
Current Status
Issued on 9/9/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/1/2024 APPLICANT
Assigned to Plan Check Engineer 4/11/2024 VIVIAN LAO
Corrections Issued 5/21/2024 VIVIAN LAO
Quality Review Completed 5/24/2024 MICHAEL PEREZ
Applicant returned to address corrections 7/16/2024 VIVIAN LAO
Applicant returned to address corrections 8/13/2024 VIVIAN LAO
Applicant returned to address corrections 9/4/2024 VIVIAN LAO
Plan Check Approved 9/5/2024 VIVIAN LAO
Issued 9/9/2024 APPLICANT

Permit Application Clearance Information

No Data Available.

Contact Information

Architect Cung,, Thiep Hoang; Lic. No.: NA18995       ,
Contractor Kc Design & Construction Inc; Lic. No.: 1105511-B       ,
Engineer Allshouse,, Michael D; Lic. No.: NA62506       ,
Engineer Daugherty,, Daniel Thomas; Lic. No.: C76588 31129 VIA COLINAS STE 707      WESTLAKE VILLAGE, CA 91362
Geologist Daugherty,, Daniel Thomas; Lic. No.: EG2569 31129 VIA COLINAS SUITE 707      WESTLAKE VILLAGE, CA 91362

Inspector Information

BRENDAN MORELLI, (213) 202-3412 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

Interior/Exterior Lathing 6/9/2026   

Inspection Request History

Pre-Inspection 9/11/2024 Partial Inspection RAUL BARAJAS
Deputy Reinf. Concrete 9/27/2024 Conditional Approval RAUL BARAJAS
Footing/Foundation/Slab 9/27/2024 Partial Approval RAUL BARAJAS
Deputy Grading 10/18/2024 Conditional Approval RAUL BARAJAS
Piling/Pier/Caisson 10/25/2024 Corrections Issued RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 11/26/2024 Corrections Issued RAUL BARAJAS
Footing/Foundation/Slab 12/4/2024 Partial Inspection RAUL BARAJAS
PLUMBING-Rough 12/4/2024 Partial Approval RAUL BARAJAS
ELECTRICAL-Rough 3/13/2025 Approved ROY SPAULDING
HVAC-Rough 3/13/2025 Partial Approval ROY SPAULDING
PLUMBING-Rough 3/13/2025 Approved ROY SPAULDING
HVAC-Rough 9/3/2025 Partial Inspection RAUL BARAJAS
Deputy Drilled-In Anchors 9/19/2025 Conditional Approval ROY SPAULDING
PLUMBING-Rough 9/23/2025 Corrections Issued JOSH MEISTER
Footing/Foundation/Slab 9/26/2025 Approved DAVID WILLIAMS
PLUMBING-Rough 10/2/2025 Partial Approval ROY SPAULDING
Deputy Drilled-In Anchors 10/24/2025 Conditional Approval ROY SPAULDING
Excavation/Setback/Form/Re-Bar 10/30/2025 Corrections Issued CRAIG VAUGHAN
Deputy Drilled-In Anchors 11/12/2025 Conditional Approval ALEX COLIN
PLUMBING-Rough 11/13/2025 Corrections Issued DAVID WILLIAMS
Excavation/Setback/Form/Re-Bar 12/1/2025 Partial Approval CRAIG VAUGHAN
Footing/Foundation/Slab 12/1/2025 Corrections Issued CRAIG VAUGHAN
Footing/Foundation/Slab 12/17/2025 Partial Approval DAVID WILLIAMS
Excavation/Setback/Form/Re-Bar 1/12/2026 Corrections Issued DAVID WILLIAMS
PLUMBING-Rough 2/18/2026 Partial Approval DAVID WILLIAMS
BUILDING-Rough-Frame 5/11/2026 Corrections Issued BRENDAN MORELLI
ELECTRICAL-Rough 5/11/2026 Not Ready for Inspection BRENDAN MORELLI
Green Building Rough 5/11/2026 Not Ready for Inspection BRENDAN MORELLI
HVAC-Rough 5/11/2026 Approved BRENDAN MORELLI
Verify Sprinkler Sign Off 5/11/2026 Approved BRENDAN MORELLI
BUILDING-Rough-Frame 5/26/2026 Not Ready for Inspection BRENDAN MORELLI
ELECTRICAL-Rough 5/26/2026 Approved BRENDAN MORELLI
Green Building Rough 5/26/2026 Not Ready for Inspection BRENDAN MORELLI
Interior/Exterior Lathing 5/29/2026 Not Ready for Inspection BRENDAN MORELLI
BUILDING-Rough-Frame 6/3/2026 Partial Approval BRENDAN MORELLI
Interior/Exterior Lathing 6/3/2026 Not Ready for Inspection BRENDAN MORELLI