717 E 99TH ST 90002

Certificate Information: 717 E 99TH ST 90002

Application / Permit
22014-10001-01639
Plan Check / Job No.
B22LA25449
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
SUPPLEMENTAL TO PERMIT# 22014-10000-01639 TO REVISE SCOPE OF WORK TO " ADD 19'-5" x 14'-3" TO AND CONVERT 20'-2" x 18'-3" EX DETACHED GARAGE INTO A NEW ACCESSORY DWELLING UNIT PER LAMC 12.22A.33(c)-(d)."
Permit Issued
Issued on 1/11/2023
Issuing Office
Current Status
CofO Issued on 8/11/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/20/2022 APPLICANT
Assigned to Plan Check Engineer 12/21/2022 SARKIS HARABEDIAN
Plan Check Approved 12/22/2022 SARKIS HARABEDIAN
Issued 1/11/2023 APPLICANT
CofO in Progress 5/22/2025 JOHN KLARIN
Permit Finaled 8/11/2025 ANSON MAGLASANG
CofO Issued 8/11/2025 ANSON MAGLASANG
Permit Finaled 8/11/2025 ANSON MAGLASANG

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor L A Developing Inc; Lic. No.: 1083426-B       ,
Engineer Grigoryan,, Souren; Lic. No.: C93320 6506 TEESDALE AVE      NORTH HOLLYWOOD, CA 91606

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 2/6/2023 Partial Approval JOHN KLARIN
Deputy Drilled-In Anchors 2/13/2023 Approved JOHN KLARIN
Excavation/Setback/Form/Re-Bar 2/13/2023 Approved JOHN KLARIN
Footing/Foundation/Slab 2/13/2023 Approved JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 3/7/2023 Corrections Issued JOHN KLARIN
Wood Frame 3/8/2023 Not Ready for Inspection JOHN KLARIN
ELECTRICAL-Rough 3/30/2023 Approved JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 3/30/2023 Approved JOHN KLARIN
HVAC-Rough 3/30/2023 Approved JOHN KLARIN
PLUMBING-Rough 3/30/2023 Approved JOHN KLARIN
Insulation 4/4/2023 Approved JOHN KLARIN
Interior/Exterior Lathing 4/4/2023 Approved JOHN KLARIN
Drywall Nailing 4/17/2023 Approved JAMES CHAVEZ
BUILDING-Rough-Frame 7/14/2023 Approved JOHN KLARIN
Final 7/14/2023 Corrections Issued JOHN KLARIN
Green Building Final 7/14/2023 Corrections Issued JOHN KLARIN
Green Building Rough 7/14/2023 Approved JOHN KLARIN
Smoke Detectors 7/14/2023 Approved JOHN KLARIN
Final 7/28/2023 Corrections Issued JOHN KLARIN
Green Building Final 7/28/2023 Approved JOHN KLARIN
Final 2/26/2025 Corrections Issued BEN MOLSTAD
Final 3/11/2025 Corrections Issued ANTHONY EGSON
Final 4/23/2025 Corrections Issued ANTHONY EGSON
Final 5/19/2025 No Access for Inspection ANTHONY EGSON
ELECTRICAL-Final 5/21/2025 Approved JOHN KLARIN
Final 5/21/2025 OK to Issue CofO JOHN KLARIN
HVAC-Final 5/21/2025 Approved JOHN KLARIN
PLUMBING-Final 5/21/2025 Approved JOHN KLARIN