4517 W DUNDEE DR 90027
Certificate Information: 4517 W DUNDEE DR 90027
- Application / Permit
- 22014-10000-06361
- Plan Check / Job No.
- B22LA26500
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL AND 106 SF ADDITION TO EXISTING SFD W/ ATTACHED GARAGE
- Permit Issued
- Issued on 4/7/2023
- Issuing Office
- Current Status
- CofO Issued on 3/24/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/29/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/19/2023 | CRYSTEL MAALOUF |
| Corrections Issued | 1/30/2023 | CRYSTEL MAALOUF |
| Quality Review Completed | 2/7/2023 | KEN GILL |
| Building Plans Picked Up | 2/9/2023 | APPLICANT |
| Plan Check Approved | 3/7/2023 | CRYSTEL MAALOUF |
| Issued | 4/7/2023 | APPLICANT |
| CofO in Progress | 3/12/2026 | ENRIQUE MIRELES |
| No Progress | 3/13/2026 | DEROLD HAUFF |
| CofO in Progress | 3/13/2026 | DEROLD HAUFF |
| Permit Finaled | 3/24/2026 | DEROLD HAUFF |
| CofO Issued | 3/24/2026 | DEROLD HAUFF |
| Permit Finaled | 3/24/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 2/25/2023 | TREVOR QUAN |
| Sewer availability | Cleared | 2/25/2023 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 2/28/2023 | TREVOR QUAN |
| GPI Written Notices | Cleared | 3/7/2023 | CRYSTEL MAALOUF |
| Grading Pre-Inspection | Cleared | 3/7/2023 | CRYSTEL MAALOUF |
Contact Information
| Architect | Bestor,, Barbara A; Lic. No.: C26132 | 2030 HYPERION AVENUE LOS ANGELES, CA 90027 |
| Contractor | Luis Chavez Construction Inc; Lic. No.: 1024942-B | P O BOX 36824 LOS ANGELES, CA 90036 |
| Engineer | Phillips,, Craig; Lic. No.: C69673 | 2123 VESTAL AVE LOS ANGELES, CA 90026 |
Inspector Information
| ENRIQUE MIRELES, (213) 202-3438 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 8/8/2023 | Approved | JOSEPH MCGARRY |
| Underground Mechanical | 8/8/2023 | Partial Approval | JOSEPH MCGARRY |
| Deputy Drilled-In Anchors | 8/10/2023 | Partial Approval | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 8/14/2023 | Partial Approval | JOSEPH MCGARRY |
| Deputy Drilled-In Anchors | 8/15/2023 | Partial Approval | JOSEPH MCGARRY |
| Deputy Reinf. Concrete | 10/2/2023 | Conditional Approval | JOSH MEISTER |
| Deputy Drilled-In Anchors | 10/6/2023 | Partial Approval | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 10/16/2023 | Approved | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 1/8/2024 | Corrections Issued | BRENDAN MORELLI |
| Deputy Steel/Welding | 1/12/2024 | Partial Approval | JEFFREY MEAD |
| Deputy Wood Construction | 1/16/2024 | Partial Approval | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 1/19/2024 | Partial Approval | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 1/31/2024 | Approved | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 6/12/2024 | Partial Approval | BRENDAN MORELLI |
| PLUMBING-Rough | 6/12/2024 | Corrections Issued | BRENDAN MORELLI |
| Interior/Exterior Lathing | 7/2/2024 | Not Ready for Inspection | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 7/8/2024 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 2/11/2025 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 2/11/2025 | Approved | ENRIQUE MIRELES |
| HVAC-Rough | 2/11/2025 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 2/11/2025 | Approved | ENRIQUE MIRELES |
| Insulation | 3/5/2025 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 3/13/2025 | Approved | ENRIQUE MIRELES |
| Shower Pan | 6/10/2025 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 6/24/2025 | Approved | ALEX COLIN |
| Underground Mechanical | 8/12/2025 | Approved | ENRIQUE MIRELES |
| HVAC-Final | 3/3/2026 | Corrections Issued | ENRIQUE MIRELES |
| ELECTRICAL-Final | 3/4/2026 | Approved | ENRIQUE MIRELES |
| Service/Power Release | 3/4/2026 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Final | 3/5/2026 | Approved | BRENDAN MORELLI |
| HVAC-Final | 3/5/2026 | Approved | BRENDAN MORELLI |
| PLUMBING-Final | 3/5/2026 | Approved | BRENDAN MORELLI |
| Final | 3/10/2026 | OK to Issue CofO | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 3/10/2026 | SGSOV Approved | ENRIQUE MIRELES |
| Smoke Detectors | 3/10/2026 | Approved | ENRIQUE MIRELES |