2614 S ARMACOST AVE 90064

Certificate Information: 2614 S ARMACOST AVE 90064

Application / Permit
22014-10000-06352
Plan Check / Job No.
B22LA26452
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePLAN- Major remodel and 1 story addition to (e) SFD
Permit Issued
Issued on 7/19/2024
Issuing Office
Current Status
CofO Issued on 12/12/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/29/2022 APPLICANT
Assigned to Plan Check Engineer 2/2/2023 MARCELA FRANQUEZ
Corrections Issued 2/4/2023 MARCELA FRANQUEZ
Quality Review Completed 2/21/2023 TEODORO DIAZ RODRIGUEZ
Plan Check Approved 5/10/2023 MARCELA FRANQUEZ
Issued 7/19/2024 APPLICANT
CofO in Progress 11/30/2025 KIRK SANDERS
Permit Finaled 12/12/2025 RICHARD STEINBACH
CofO Issued 12/12/2025 RICHARD STEINBACH
Permit Finaled 12/12/2025 RICHARD STEINBACH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 4/18/2023 JASON NG
Roof/Waste drainage to street Cleared 4/18/2023 JASON NG
Sewer availability Cleared 4/18/2023 JASON NG
Roof/Waste drainage to street Cleared 3/9/2024 BRENDEN HAWK
Sewer availability Cleared 3/9/2024 BRENDEN HAWK

Contact Information

Architect Keck,, Krystyan Elizabeth; Lic. No.: NA29385       ,
Contractor Integrity Remodeling; Lic. No.: 822562-B       ,
Engineer Lotfi,, Fariborz F; Lic. No.: NA49359       ,

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 8/26/2024 No Access for Inspection DANIEL VERA
Footing/Foundation/Slab 9/12/2024 Approved DANIEL VERA
PLUMBING-Rough 10/21/2024 Partial Approval DANIEL VERA
Floor/Roof Diaphrgm/Shear Wall 10/30/2024 Approved DANIEL VERA
Floor/Roof Diaphrgm/Shear Wall 1/27/2025 Approved DANIEL VERA
PLUMBING-Rough 1/27/2025 Approved DANIEL VERA
BUILDING-Rough-Frame 5/16/2025 Approved WILBER ROSALES
ELECTRICAL-Rough 5/16/2025 Approved WILBER ROSALES
Green Building Rough 5/16/2025 Approved WILBER ROSALES
HVAC-Rough 5/16/2025 Approved WILBER ROSALES
Insulation 5/28/2025 Corrections Issued WILBER ROSALES
Drywall Nailing 6/2/2025 Approved WILBER ROSALES
Insulation 6/2/2025 Approved WILBER ROSALES
Shower Pan 6/2/2025 Approved WILBER ROSALES
Interior/Exterior Lathing 6/6/2025 Approved WILBER ROSALES
ELECTRICAL-Final 11/14/2025 Approved KIRK SANDERS
Final 11/14/2025 Corrections Issued KIRK SANDERS
HVAC-Final 11/14/2025 Corrections Issued KIRK SANDERS
PLUMBING-Final 11/14/2025 Approved KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 11/14/2025 SGSOV Approved KIRK SANDERS
Smoke Detectors 11/14/2025 Approved KIRK SANDERS
Final 11/26/2025 OK to Issue CofO KIRK SANDERS
Green Building Final 11/26/2025 Approved KIRK SANDERS