5142 W LOS DIEGOS WAY 90027

Certificate Information: 5142 W LOS DIEGOS WAY 90027

Application / Permit
22014-10000-06343
Plan Check / Job No.
B22LA26386
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePLAN- ENTRY PORCH ADDITION AND MAJOR REMODEL OF 2-STORY SFD/GARAGE • COMPLETE REMODEL • ENTRY ADDITION: 67 SF • ELECTRICAL ROOM CONVERSION: 59 SF
Permit Issued
Issued on 3/30/2023
Issuing Office
Current Status
CofO Issued on 12/1/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/29/2022 APPLICANT
Assigned to Plan Check Engineer 1/19/2023 YASHAR EMAMI
Corrections Issued 1/21/2023 YASHAR EMAMI
Plans on Hold 2/3/2023 CHIHARU SUZUKI
Hold Released 2/14/2023 CHIHARU SUZUKI
Quality Review Completed 2/14/2023 CHIHARU SUZUKI
Applicant returned to address corrections 3/14/2023 YASHAR EMAMI
Plan Check Approved 3/23/2023 YASHAR EMAMI
Issued 3/30/2023 APPLICANT
CofO in Progress 11/26/2024 CRAIG VAUGHAN
Permit Finaled 12/1/2024 DEROLD HAUFF
CofO Issued 12/1/2024 DEROLD HAUFF
Permit Finaled 12/1/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 2/9/2023 AMAAN MALIK
BHO/Hillside ordinance Cleared 2/9/2023 AMAAN MALIK
BHO/Hillside ordinance Cleared 2/9/2023 AMAAN MALIK
BHO/Hillside ordinance Cleared 2/9/2023 AMAAN MALIK
BHO/Hillside ordinance Cleared 2/9/2023 AMAAN MALIK
Roof/Waste drainage to street Cleared 2/9/2023 AMAAN MALIK
ZI Cleared 2/9/2023 NOAH MCCOY
Eng Process Fee Ord 176,300 Cleared 2/10/2023 AMAAN MALIK
BHO/Hillside ordinance Cleared 2/14/2023 WALLIE JONG
Sewer availability Cleared 2/21/2023 WALLIE JONG
Grading Pre-Inspection Cleared 3/14/2023 YASHAR EMAMI

Contact Information

Contractor Ryan Tim Construction Inc; Lic. No.: 782337-B 125 E SANTA CLARA STREET #19      ARCADIA, CA 91006
Engineer Chiu,, Ivan Wai-Kuen; Lic. No.: C44672 2160 PARNELL WY      ALTADENA, CA 91001

Inspector Information

CRAIG VAUGHAN, (213) 202-3250 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/3/2023 Conditional Approval JOAQUIN GREENOUGH
Footing/Foundation/Slab 5/4/2023 Approved JOAQUIN GREENOUGH
Deputy Drilled-In Anchors 6/13/2023 Conditional Approval JOAQUIN GREENOUGH
BUILDING-Rough-Frame 7/24/2023 Not Ready for Inspection STUART CHAPMAN
PLUMBING-Rough 7/24/2023 Corrections Issued STUART CHAPMAN
Wood Frame 7/24/2023 Not Ready for Inspection STUART CHAPMAN
PLUMBING-Rough 7/28/2023 Partial Approval STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 8/10/2023 Corrections Issued JOAQUIN GREENOUGH
BUILDING-Rough-Frame 8/18/2023 Corrections Issued JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 8/18/2023 Corrections Issued JOAQUIN GREENOUGH
BUILDING-Rough-Frame 8/31/2023 Partial Approval STUART CHAPMAN
Deputy Wood Construction 8/31/2023 Conditional Approval JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 8/31/2023 Partial Approval STUART CHAPMAN
Wood Frame 8/31/2023 Partial Approval STUART CHAPMAN
ELECTRICAL-Rough 9/25/2023 Not Ready for Inspection JOAQUIN GREENOUGH
HVAC-Rough 9/25/2023 Approved JOAQUIN GREENOUGH
Interior/Exterior Lathing 9/25/2023 Partial Approval JOAQUIN GREENOUGH
PLUMBING-Rough 9/25/2023 Not Ready for Inspection JOAQUIN GREENOUGH
ELECTRICAL-Rough 10/3/2023 Corrections Issued JOAQUIN GREENOUGH
HVAC-Rough 10/3/2023 Approved JOAQUIN GREENOUGH
PLUMBING-Rough 10/3/2023 Not Ready for Inspection JOAQUIN GREENOUGH
ELECTRICAL-Rough 10/10/2023 Not Ready for Inspection JOAQUIN GREENOUGH
HVAC-Rough 10/10/2023 Not Ready for Inspection JOAQUIN GREENOUGH
PLUMBING-Rough 10/10/2023 Not Ready for Inspection JOAQUIN GREENOUGH
BUILDING-Rough-Frame 10/12/2023 Not Ready for Inspection JOAQUIN GREENOUGH
ELECTRICAL-Rough 10/12/2023 Approved JOAQUIN GREENOUGH
HVAC-Rough 10/12/2023 Approved JOAQUIN GREENOUGH
PLUMBING-Rough 10/12/2023 Approved JOAQUIN GREENOUGH
Wood Frame 10/12/2023 Not Ready for Inspection JOAQUIN GREENOUGH
BUILDING-Rough-Frame 10/16/2023 Corrections Issued JOAQUIN GREENOUGH
Wood Frame 10/16/2023 Not Ready for Inspection JOAQUIN GREENOUGH
BUILDING-Rough-Frame 12/8/2023 Approved JOAQUIN GREENOUGH
Wood Frame 12/8/2023 Approved JOAQUIN GREENOUGH
Insulation 12/15/2023 Approved BRIAN SULLIVAN
Shower Pan 12/15/2023 Approved BRIAN SULLIVAN
Drywall Nailing 12/26/2023 Approved ALIZAH MAYAGOITIA
Interior/Exterior Lathing 12/29/2023 Partial Approval STUART CHAPMAN
Interior/Exterior Lathing 1/4/2024 Approved BRIAN SULLIVAN
ELECTRICAL-Final 8/20/2024 Not Ready for Inspection ROY SPAULDING
HVAC-Final 8/20/2024 Not Ready for Inspection ROY SPAULDING
PLUMBING-Final 8/20/2024 Not Ready for Inspection ROY SPAULDING
ELECTRICAL-Final 8/27/2024 Corrections Issued ROY SPAULDING
HVAC-Final 8/27/2024 Approved ROY SPAULDING
PLUMBING-Final 8/27/2024 Approved ROY SPAULDING
ELECTRICAL-Final 8/30/2024 Approved ROY SPAULDING
Final 8/30/2024 Conditional Approval ROY SPAULDING
HVAC-Final 8/30/2024 Approved ROY SPAULDING
PLUMBING-Final 8/30/2024 Approved ROY SPAULDING
SGSOV-Seismic Gas S/O Valve 8/30/2024 SGSOV Approved ROY SPAULDING
Smoke Detectors 8/30/2024 Approved ROY SPAULDING
Final 10/24/2024 Conditional Approval CRAIG VAUGHAN
Final 10/30/2024 Corrections Issued CRAIG VAUGHAN
Final 11/5/2024 OK to Issue CofO CRAIG VAUGHAN