1251 W 19TH ST 90731
Certificate Information: 1251 W 19TH ST 90731
- Application / Permit
- 22014-10000-06341
- Plan Check / Job No.
- B22LA26381
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: Convert Crawl space & rumpus room into an ADU ADU CHECKED PER LAMC 12.22 A.33(C) AND (E)
- Permit Issued
- Issued on 11/10/2023
- Issuing Office
- Current Status
- CofO Issued on 3/17/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/28/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/2/2023 | SUNMIN LEE |
| Corrections Issued | 2/3/2023 | SUNMIN LEE |
| Quality Review Completed | 2/3/2023 | GARO TELMI |
| Applicant returned to address corrections | 8/17/2023 | SUNMIN LEE |
| Applicant returned to address corrections | 10/17/2023 | SUNMIN LEE |
| Applicant returned to address corrections | 10/30/2023 | SUNMIN LEE |
| Plan Check Approved | 11/9/2023 | SUNMIN LEE |
| Issued | 11/10/2023 | APPLICANT |
| Refund in Progress | 7/30/2024 | SELENIA GARCIA |
| Refund Denied | 9/5/2024 | EMILY HU |
| Issued | 9/5/2024 | EMILY HU |
| CofO in Progress | 3/10/2025 | JOSEPH MCGARRY |
| Permit Finaled | 3/17/2025 | ANSON MAGLASANG |
| CofO Issued | 3/17/2025 | ANSON MAGLASANG |
| Permit Finaled | 3/17/2025 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 2/23/2023 | KHAING AYE |
| Sewer availability | Cleared | 2/23/2023 | KHAING AYE |
| Eng Process Fee Ord 176,300 | Cleared | 3/2/2023 | KHAING AYE |
| Grading Pre-Inspection | Cleared | 8/18/2023 | SUNMIN LEE |
| Roof/Waste drainage to street | Cleared | 8/21/2023 | KHAING AYE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Itani,, Riad Hassan; Lic. No.: C55688 | 2459 W 228TH ST TORRANCE, CA 90501 |
Inspector Information
| JOSEPH MCGARRY, (310) 732-4559 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/6/2024 | Partial Inspection | JAMES CHAVEZ |
| BUILDING-Rough-Frame | 12/2/2024 | Corrections Issued | BEN MOLSTAD |
| ELECTRICAL-Rough | 12/2/2024 | Corrections Issued | BEN MOLSTAD |
| Gas Test | 12/2/2024 | Approved | BEN MOLSTAD |
| PLUMBING-Rough | 12/2/2024 | Approved | BEN MOLSTAD |
| ELECTRICAL-Rough | 12/10/2024 | Approved | BEN MOLSTAD |
| BUILDING-Rough-Frame | 12/17/2024 | Corrections Issued | JOSEPH MCGARRY |
| HVAC-Rough | 12/17/2024 | Approved | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 12/24/2024 | Approved | JOSEPH MCGARRY |
| Insulation | 12/24/2024 | Approved | JOSEPH MCGARRY |
| Drywall Nailing | 1/2/2025 | Approved | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 1/2/2025 | Partial Approval | JOSEPH MCGARRY |
| Shower Pan | 1/2/2025 | Approved | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 1/7/2025 | Approved | JOSEPH MCGARRY |
| Final | 2/28/2025 | Corrections Issued | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 2/28/2025 | Approved | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 2/28/2025 | SGSOV Approved | JOSEPH MCGARRY |
| Smoke Detectors | 2/28/2025 | Approved | JOSEPH MCGARRY |
| Final | 3/7/2025 | OK to Issue CofO | JOSEPH MCGARRY |