732 N HAMPDEN PL 90272
Certificate Information: 732 N HAMPDEN PL 90272
- Application / Permit
- 22014-10000-06325
- Plan Check / Job No.
- B22LA26341
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- *EPLAN* GROUND FLOOR ADDITION (400 SF) WITH ROOF DECK TO (E) SFD.
- Permit Issued
- Issued on 4/6/2023
- Issuing Office
- Current Status
- CofO Issued on 4/12/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/28/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/12/2023 | VIVIAN LAO |
| Corrections Issued | 1/19/2023 | VIVIAN LAO |
| Quality Review Completed | 1/19/2023 | GARO TELMI |
| Plan Check Approved | 3/9/2023 | VIVIAN LAO |
| Issued | 4/6/2023 | APPLICANT |
| CofO in Progress | 4/5/2024 | EVAN COOPER |
| Permit Finaled | 4/12/2024 | DANIEL ORRANTE |
| CofO Issued | 4/12/2024 | DANIEL ORRANTE |
| Permit Finaled | 4/12/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 1/26/2023 | JENSON LEE |
| Roof/Waste drainage to street | Cleared | 1/26/2023 | JENSON LEE |
| Watercourse | Cleared | 1/26/2023 | HISASHI KOBAYAKAWA |
| Eng Process Fee Ord 176,300 | Cleared | 2/1/2023 | JENSON LEE |
| Sewer availability | Cleared | 2/1/2023 | JENSON LEE |
| Coastal Zone | Cleared | 2/10/2023 | NOAH MCCOY |
| BHO/Hillside ordinance | Cleared | 2/24/2023 | AHMED AMARRAGY |
| BHO/Hillside ordinance | Cleared | 2/24/2023 | AHMED AMARRAGY |
| BHO/Hillside ordinance | Cleared | 2/24/2023 | AHMED AMARRAGY |
| BHO/Hillside ordinance | Cleared | 2/24/2023 | AHMED AMARRAGY |
| Grading Pre-Inspection | Cleared | 3/8/2023 | KIRK LINKLATER |
Contact Information
| Contractor | Hogan Construction And Development Inc; Lic. No.: 1085371-B | , |
| Engineer | Samara,, Muzahim; Lic. No.: NA26015 | , |
Inspector Information
| STEPHANIE SWANSON, (213) 469-1255 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/19/2023 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Piling/Pier/Caisson | 5/23/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Footing/Foundation/Slab | 6/14/2023 | No Access for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Footing/Foundation/Slab | 6/26/2023 | Conditional Approval | GERMAN RODRIGUEZ MENDOZA |
| Footing/Foundation/Slab | 7/3/2023 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Footing/Foundation/Slab | 7/13/2023 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Excavation/Setback/Form/Re-Bar | 7/17/2023 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Rough | 7/31/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/3/2023 | Partial Inspection | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Rough | 8/3/2023 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Special/Order Compliance | 8/3/2023 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Deputy Wood Construction | 8/8/2023 | Conditional Approval | GERMAN RODRIGUEZ MENDOZA |
| Floor/Roof Diaphrgm/Shear Wall | 8/8/2023 | Conditional Approval | GERMAN RODRIGUEZ MENDOZA |
| FLOOD-Proofing Certificate | 8/17/2023 | Approved | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 8/17/2023 | Partial Approval | EVAN COOPER |
| Green Building Rough | 8/17/2023 | Not Ready for Inspection | EVAN COOPER |
| Verify Sprinkler Sign Off | 8/17/2023 | Not Ready for Inspection | EVAN COOPER |
| ELECTRICAL-Rough | 8/23/2023 | Partial Approval | EVAN COOPER |
| PLUMBING-Rough | 8/23/2023 | Partial Approval | EVAN COOPER |
| Special/Order Compliance | 8/25/2023 | Corrections Issued | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 9/13/2023 | Partial Approval | EVAN COOPER |
| Interior/Exterior Lathing | 9/13/2023 | Partial Approval | EVAN COOPER |
| PLUMBING-Rough | 9/13/2023 | Partial Approval | EVAN COOPER |
| Insulation | 9/27/2023 | Approved | EVAN COOPER |
| Drywall Nailing | 10/3/2023 | Approved | EVAN COOPER |
| Green Building Rough | 10/3/2023 | Approved | EVAN COOPER |
| Shower Pan | 10/3/2023 | Not Ready for Inspection | EVAN COOPER |
| Shower Pan | 10/12/2023 | Approved | EVAN COOPER |
| HVAC-Final | 11/9/2023 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 11/16/2023 | Approved | EVAN COOPER |
| Final | 11/16/2023 | Corrections Issued | EVAN COOPER |
| HVAC-Final | 11/16/2023 | Approved | EVAN COOPER |
| PLUMBING-Final | 11/16/2023 | Approved | EVAN COOPER |
| BUILDING-Rough-Frame | 1/31/2024 | Approved | EVAN COOPER |
| Final | 1/31/2024 | Corrections Issued | EVAN COOPER |
| Footing/Foundation/Slab | 1/31/2024 | Approved | EVAN COOPER |
| Green Building Final | 1/31/2024 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 1/31/2024 | SGSOV Approved | EVAN COOPER |
| Smoke Detectors | 1/31/2024 | Approved | EVAN COOPER |
| Verify Sprinkler Sign Off | 1/31/2024 | Approved | EVAN COOPER |
| Final | 3/29/2024 | OK to Issue CofO | EVAN COOPER |