3937 N TOLAND WAY 90065

Certificate Information: 3937 N TOLAND WAY 90065

Application / Permit
22014-10000-06310
Plan Check / Job No.
B22LA26285
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan Addition and remodel (E) SFD. Per engineering design.
Permit Issued
Issued on 1/4/2024
Issuing Office
Current Status
Issued on 1/4/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/29/2022 APPLICANT
Assigned to Plan Check Engineer 1/6/2023 ALFREDO JARA
Corrections Issued 1/7/2023 ALFREDO JARA
Applicant returned to address corrections 6/21/2023 ALFREDO JARA
Plan Check Approved 9/27/2023 ALFREDO JARA
Issued 1/4/2024 APPLICANT

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 3/15/2023 STEVE MELGAR
Sewer availability Cleared 3/15/2023 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 3/20/2023 STEVE MELGAR
Grading Pre-Inspection Cleared 6/22/2023 ALFREDO JARA
Low Impact Development (LID) Cleared 9/13/2023 VICTOR MENDOZA
Specific Plan Cleared 9/25/2023 DAVID URITA
ZI Cleared 9/25/2023 DAVID URITA

Contact Information

Architect Chang,, Monica K; Lic. No.: NA37524       ,
Contractor C M J Construction Inc; Lic. No.: 1095617-B       ,
Engineer Youm,, Moung Han; Lic. No.: C74086 309 S BERENDO ST APT 6      LOS ANGELES, CA 90020

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/29/2024 Conditional Approval HAMIK HARTOUNIAN
Deputy Drilled-In Anchors 1/30/2024 Conditional Approval HAMIK HARTOUNIAN
Footing/Foundation/Slab 3/8/2024 Not Ready for Inspection BRIAN SULLIVAN
Piling/Pier/Caisson 3/8/2024 Corrections Issued BRIAN SULLIVAN
Footing/Foundation/Slab 3/15/2024 Corrections Issued HAMIK HARTOUNIAN
Piling/Pier/Caisson 3/15/2024 Not Ready for Inspection HAMIK HARTOUNIAN
Footing/Foundation/Slab 6/7/2024 Not Ready for Inspection THOMAS LOGRASSO
Footing/Foundation/Slab 6/20/2024 Approved BRIAN SULLIVAN
Piling/Pier/Caisson 6/20/2024 Approved BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 7/10/2024 Conditional Approval THOMAS LOGRASSO
PLUMBING-Rough 7/10/2024 Partial Approval THOMAS LOGRASSO
Deputy Wood Construction 8/5/2024 Conditional Approval THOMAS LOGRASSO
ELECTRICAL-Rough 12/4/2024 No Access for Inspection THOMAS LOGRASSO
Deputy Wood Construction 1/2/2025 Conditional Approval THOMAS LOGRASSO
BUILDING-Rough-Frame 1/3/2025 Corrections Issued THOMAS LOGRASSO
Rough-Elec/Plmb/HVAC 1/3/2025 Corrections Issued THOMAS LOGRASSO
BUILDING-Rough-Frame 5/9/2025 No Access for Inspection NICHOLAS LOPEZ
ELECTRICAL-Rough 5/9/2025 No Access for Inspection NICHOLAS LOPEZ
MERV13>=Rough 5/9/2025 No Access for Inspection NICHOLAS LOPEZ
PLUMBING-Rough 5/9/2025 No Access for Inspection NICHOLAS LOPEZ
BUILDING-Rough-Frame 5/21/2025 Approved NICHOLAS LOPEZ
MERV13>=Rough 5/21/2025 Approved NICHOLAS LOPEZ
Rough-Elec/Plmb/HVAC 5/21/2025 Approved NICHOLAS LOPEZ
Shower Pan 10/20/2025 Approved REGINA MENDEZ
Interior/Exterior Lathing 12/11/2025 Approved NICHOLAS LOPEZ
Insulation 12/19/2025 Partial Inspection RONNIE MEDINA
Insulation 4/22/2026 Approved LILIANA PORTILLO
Drywall Nailing 5/7/2026 Approved NICHOLAS LOPEZ
Special/Order Compliance 5/7/2026 Corrections Issued NICHOLAS LOPEZ