3285 W LARGA AVE 90039
Certificate Information: 3285 W LARGA AVE 90039
- Application / Permit
- 22014-10000-06301
- Plan Check / Job No.
- B22LA26277
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan: 751 SF SECOND STORY ADDITION TO (E) SINGLE STORY SINGLE FAMILY RESIDENCE, REMODEL KITCHEN
- Permit Issued
- Issued on 9/29/2023
- Issuing Office
- Current Status
- CofO Issued on 8/9/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/29/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/19/2023 | YASHAR EMAMI |
| Corrections Issued | 1/22/2023 | YASHAR EMAMI |
| Plans on Hold | 2/3/2023 | CHIHARU SUZUKI |
| Hold Released | 2/14/2023 | CHIHARU SUZUKI |
| Quality Review Completed | 2/14/2023 | CHIHARU SUZUKI |
| Applicant returned to address corrections | 2/15/2023 | YASHAR EMAMI |
| Applicant returned to address corrections | 5/18/2023 | YASHAR EMAMI |
| Plan Check Approved | 6/2/2023 | YASHAR EMAMI |
| Issued | 9/29/2023 | APPLICANT |
| CofO in Progress | 8/4/2025 | NICHOLAS LOPEZ |
| Permit Finaled | 8/9/2025 | DEROLD HAUFF |
| CofO Issued | 8/9/2025 | DEROLD HAUFF |
| Permit Finaled | 8/9/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/30/2023 | JEANIE LAM |
| ZI | Cleared | 3/30/2023 | KENTON TRINH |
| Roof/Waste drainage to street | Cleared | 5/11/2023 | JEANIE LAM |
| Stormwater Pollution Mitigatn | Cleared | 5/11/2023 | SARAH YOUSSEF |
Contact Information
| Architect | Rudolph,, Rebecca Alice; Lic. No.: C29756 | 3218 ATWATER AVENUE LOS ANGELES, CA 90039 |
| Contractor | Streamline Construction; Lic. No.: 923202-B | , |
| Engineer | Parker,, Leo Augustine; Lic. No.: NA2829 | , |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 11/29/2023 | Conditional Approval | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 12/4/2023 | Approved | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/14/2023 | Partial Approval | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 3/22/2024 | Approved | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/9/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/26/2024 | Partial Approval | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 5/13/2024 | Approved | THOMAS LOGRASSO |
| HVAC-Rough | 5/28/2024 | Corrections Issued | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 7/1/2024 | Corrections Issued | JOSEPH MCGARRY |
| HVAC-Rough | 7/1/2024 | Partial Approval | JOSEPH MCGARRY |
| Insulation | 7/17/2024 | Approved | BRENDAN MORELLI |
| Shower Pan | 8/9/2024 | Approved | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 8/27/2024 | Approved | CHARLES BOGHOSKHAN |
| BUILDING-Rough-Frame | 9/16/2024 | Approved | THOMAS LOGRASSO |
| Drywall Nailing | 9/16/2024 | Approved | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 3/19/2025 | Approved | NICHOLAS LOPEZ |
| Final | 3/19/2025 | Corrections Issued | NICHOLAS LOPEZ |
| Green Building Final | 3/19/2025 | Not Ready for Inspection | NICHOLAS LOPEZ |
| Green Building Rough | 3/19/2025 | Approved | NICHOLAS LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 3/19/2025 | SGSOV Not Ready | NICHOLAS LOPEZ |
| Smoke Detectors | 3/19/2025 | Corrections Issued | NICHOLAS LOPEZ |
| Final | 5/29/2025 | Corrections Issued | NICHOLAS LOPEZ |
| Green Building Final | 5/29/2025 | Approved | NICHOLAS LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 5/29/2025 | SGSOV Approved | NICHOLAS LOPEZ |
| Smoke Detectors | 5/29/2025 | Approved | NICHOLAS LOPEZ |
| Final | 8/4/2025 | OK to Issue CofO | NICHOLAS LOPEZ |